7684 :
Construction and operation of the Hydraulic Power Plant Chicoasén II
| Project title |
Construction and operation of the Hydraulic Power Plant Chicoasén II
- project design document (1152 KB)
PDD appendices Appendix 1 - Project Check List (590 KB)
Appendix 2 - Project Economic Model (367 KB)
Appendix 3 - Response for Request Incomplete (181 KB)
Appendix 4 - Appendix 4-COPAR.Cost and Parameters for the Formulation of Investment Projects in the Electricity Sector (2292 KB)
- registration request form (111 KB)
|
|---|---|
| SDC description report | Not Available. Please refer to our Further Information on SD-Tool |
| Host Parties |
Mexico
, involved indirectly
approval (2724 KB)
authorization (2724 KB)
Authorized Participants: Comisión Federal de Electricidad. ; Carbon Solutions de México S.A. de C.V. |
| Other Parties Involved | n/a |
| Sectoral scopes | 1 : Energy industries (renewable - / non-renewable sources) |
| Activity Scale | LARGE |
| Methodologies Used |
ACM0002 ver. 12 -
Consolidated baseline methodology for grid-connected electricity generation from renewable sources
|
| Standardized baselines used | N/A |
| Amount of Reductions | 299,436 metric tonnes CO2 equivalent per annum |
| Fee level | USD 58387.2 |
| Validation Report |
VVS/VVM version:
VVM 1.2
Validation report (468 KB)
Public availability information
Link to information uploaded for public availability |
| Modalities of Communication | |
| Registration Date | Rejected (view history) completeness check: complete info & rep check: concluded |
| Crediting Period | 01 Jul 17 - 30 Jun 26 (Fixed) |