Project 7684 : Construction and operation of the Hydraulic Power Plant Chicoasén II
Project title Construction and operation of the Hydraulic Power Plant Chicoasén II
- project design document (1152 KB)

PDD appendices
Appendix 1 - Project Check List (590 KB)
Appendix 2 - Project Economic Model (367 KB)
Appendix 3 - Response for Request Incomplete (181 KB)
Appendix 4 - Appendix 4-COPAR.Cost and Parameters for the Formulation of Investment Projects in the Electricity Sector (2292 KB)


- registration request form (111 KB)
SDC description report Not Available. Please refer to our Further Information on SD-Tool
Host Parties Mexico , involved indirectly approval (2724 KB) authorization (2724 KB)
Authorized Participants: Comisión Federal de Electricidad. ; Carbon Solutions de México S.A. de C.V.
Other Parties Involved n/a
Sectoral scopes 1 : Energy industries (renewable - / non-renewable sources)
Activity Scale LARGE
Methodologies Used ACM0002 ver. 12 - Consolidated baseline methodology for grid-connected electricity generation from renewable sources
Standardized baselines used N/A
Amount of Reductions 299,436 metric tonnes CO2 equivalent per annum
Fee level USD 58387.2
Validation Report VVS/VVM version: VVM 1.2
Validation report (468 KB) Public availability information
Link to information uploaded for public availability
Modalities of Communication
Registration Date Rejected   (view history)   completeness check: complete info & rep check: concluded