15:59 08 Feb 26
Project:
3599 Bajo Tuluá Minor Hydroelectric Power Plant
- Issuance Request
| Project | 3599: Bajo Tuluá Minor Hydroelectric Power Plant |
|---|---|
| ISSUANCE STATUS | Issued (on 13 Aug 19) completeness check: complete | info & rep check: concluded |
| Monitoring period | 29 Nov 11 - 31 Dec 17 |
| Monitoring report |
Monitoring report (471 KB)
|
| Submission of comments to the DOE | |
| Requests for post-registration changes containing applicable deviations | PRC-3599-001 - Approved |
| Requests for post-registration changes submitted with the issuance request | PRC-3599-001 |
| Request for issuance |
Signed form (138 KB)
|
| Amount of CERs |
CERs issued up to 31 December 2012:
0
CERs issued from 01 Jan 2013 until 31 December 2020: 74,875 Total amount of CERs: 74,875
Serial Range:
Block start: CO-5-14700866-2-2-0-3599
Block end: CO-5-14775740-2-2-0-3599
|
| Verification and certification reports |
VVS/VVM version:
VVS-PA 2.0
Certification report (685 KB)
Verification report (685 KB)
|
| Additional documents |
3599 CER calculation.xlsx (5228 KB)
3599 Monitoring Report.pdf (773 KB)
|

Monitoring report
3599 CER calculation.xlsx