07:55 04 Nov 25
			
			
      Project: 
      3599 Bajo Tuluá Minor Hydroelectric Power Plant
      - Issuance Request
    
					| Project | 3599: Bajo Tuluá Minor Hydroelectric Power Plant | 
|---|---|
| ISSUANCE STATUS | Issued (on 13 Aug 19) completeness check: complete | info & rep check: concluded | 
| Monitoring period | 29 Nov 11 - 31 Dec 17 | 
| Monitoring report | 
             Monitoring report (471 KB)
           | 
        
| Submission of comments to the DOE | |
| Requests for post-registration changes containing applicable deviations | PRC-3599-001 - Approved | 
| Requests for post-registration changes submitted with the issuance request | PRC-3599-001 | 
| Request for issuance | 
                 Signed form (138 KB)
                
                
               | 
            
| Amount of CERs | 
                
                  CERs issued up to 31 December 2012:
                  0
                   CERs issued from 01 Jan 2013 until 31 December 2020: 74,875 Total amount of CERs: 74,875 
  
  Serial Range:
  Block start: CO-5-14700866-2-2-0-3599    
  Block end: CO-5-14775740-2-2-0-3599
  
  
 
                
                
                
               | 
            
| Verification and certification reports | 
                
                   VVS/VVM version: 
                  VVS-PA 2.0
                   Certification report (685 KB)
                 Verification report (685 KB)
                
                
                  
               | 
            
| Additional documents | 
                
                   3599 CER calculation.xlsx (5228 KB)
                   3599 Monitoring Report.pdf (773 KB)
                  
                
                
               | 
            

Monitoring report
3599 CER calculation.xlsx