19:23 09 Jan 25
Project:
3599 Bajo Tuluá Minor Hydroelectric Power Plant
- Request for post-registration changes
Project | 3599 Bajo Tuluá Minor Hydroelectric Power Plant |
---|---|
PRC ref | PRC-3599-001 |
Process track | Issuance |
DOE | Earthood |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
No changes |
Methodology(ies) list | |
Standardized baseline(s) list | |
DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
Type of submission |
Temporary deviations from the monitoring plan or the monitoring methodology
Permanent changes from the monitoring plan or the monitoring methodology
Changes to the project or programme design
|
Applicable crediting period | 29 Nov 11 - 28 Nov 18 |
Assessment opinion | Assessment opinion (259 KB) |
Revised PDD | Revised PDD (1730 KB) Revised PDD - track changes (1734 KB) |
Supplementary documents | |
Signed form | Signed form (117 KB) |
DOE clarification | |
VVS version | VVS-PA 2.0 |
Current status | 13 Aug 19 -
Approved
Effective approval date: 13 Aug 19
|
Historic statuses |
15 Jul 19 -
Request published |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: