Project: 2761 Conversion of existing open cycle gas turbine to combined cycle at Guaracachi power station, Santa Cruz, Bolivia - Request for post-registration changes
Project 2761 Conversion of existing open cycle gas turbine to combined cycle at Guaracachi power station, Santa Cruz, Bolivia
PRC ref PRC-2761-002
Process track Prior approval
DOE TÜV NORD
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes Prior to commencement of a verification for the project activity or PoA stated above
Type of submission Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard? No

Changes to the project or programme design
  • Changes have an impact on: None of the above
Applicable crediting period 13 Apr 10 - 12 Apr 17
Assessment opinion Assessment opinion (554 KB)
Revised PDD Revised PDD (1424 KB)   Revised PDD - track changes (1644 KB)
Supplementary documents Appendix 1 - 2761 1 CER Calculation.xls (170 KB)
Signed form Signed form (55 KB)
DOE clarification
VVS version VVS 2.0
Current status 30 Jan 14 - Approved
Effective approval date: 30 Jan 14
Historic statuses 06 Jan 14 - Published
06 Jan 14 - Summary note being prepared
09 Jan 14 - Awaiting EB decision