10:01 10 Jan 25
Project:
2761 Conversion of existing open cycle gas turbine to combined cycle at Guaracachi power station, Santa Cruz, Bolivia
- Request for post-registration changes
Project | 2761 Conversion of existing open cycle gas turbine to combined cycle at Guaracachi power station, Santa Cruz, Bolivia |
---|---|
PRC ref | PRC-2761-002 |
Process track | Prior approval |
DOE | TÜV NORD |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
Methodology(ies) list | |
Standardized baseline(s) list | |
DOE conducted validation of the changes | Prior to commencement of a verification for the project activity or PoA stated above |
Type of submission |
Permanent changes from the monitoring plan or the monitoring methodology
Changes to the project or programme design
|
Applicable crediting period | 13 Apr 10 - 12 Apr 17 |
Assessment opinion | Assessment opinion (554 KB) |
Revised PDD | Revised PDD (1424 KB) Revised PDD - track changes (1644 KB) |
Supplementary documents |
Appendix 1 - 2761 1 CER Calculation.xls (170 KB)
|
Signed form | Signed form (55 KB) |
DOE clarification | |
VVS version | VVS 2.0 |
Current status | 30 Jan 14 -
Approved
Effective approval date: 30 Jan 14
|
Historic statuses |
06 Jan 14 -
Published 06 Jan 14 - Summary note being prepared 09 Jan 14 - Awaiting EB decision |
Offset now: visit the United Nations Carbon Offset Platform