16:22 19 May 25
Project:
7789 Punta Pereira biomass power plant.
- Request for post-registration changes
Project | 7789 Punta Pereira biomass power plant. |
---|---|
PRC ref | PRC-7789-002 |
Process track | Issuance |
DOE | Earthood |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
No changes |
Methodology(ies) list | |
Standardized baseline(s) list | |
DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
Type of submission |
Temporary deviations from the monitoring plan or the monitoring methodology
|
Assessment opinion |
![]() |
Revised PDD | |
Supplementary documents | |
Signed form |
![]() |
DOE clarification | |
VVS version | VVS-PA 2.0 |
Current status | 28 Oct 21 -
Approved
Effective approval date: 28 Oct 21
|
Historic statuses |
30 Sep 21 -
Request published |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: