14:24 11 Jul 24
Project:
9957 Inner Mongolia Zhuozi Bayin Solar Power Plant Project
- Crediting Period Renewal Request
[]
Project |
9957: Inner Mongolia Zhuozi Bayin Solar Power Plant Project
- ![]() PDD appendices ![]() - ![]() |
---|---|
Methodologies Used |
AMS-I.D. ver. 18 -
Grid connected renewable electricity generation
|
VVS Version | VVS-PA 2.0 |
Standardized baselines used | N/A |
Amount of Reductions | 13,027 metric tonnes CO2 equivalent per annum |
Validation Opinion |
![]() |
Renewal Date | (Renewable) Rejected (view history) completeness check: complete info & rep check: concluded |
Crediting Period (requested for renewal) |
15 May 21 - 14 May 28
Other crediting period(s): 15 May 14 - 14 May 21 |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: