Utilization of BF Gas for Steam Generation at ESSAR Steel Hazira Limited
[]
Host party(ies) India
Methodology(ies) ACM0012 ver. 3
Standardised Baselines N/A
Estimated annual reductions* 396,923
Start date of first crediting period. 01 Jun 10
Length of first crediting period. 10 years
DOE/AE DNV-CUK
Period for comments 01 Apr 10 - 30 Apr 10
PP(s) for which DOE have a contractual obligation Nordjysk Elhandel
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (1441 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
DOE is requested to consider the following comments:

1. PP argues, the steam in the baseline would have been generated from a coal fired boiler. PP is requested to show any steel industry operating blast furnace who flares the blast furnace gas without using it. The blast furnace gas has a usable calorific value which PP cant afford to waste. At least the BF gas is used in the hot stoves. DOE is requested to critically examine this claim by PP. Also check the arrangements at other plants of Essar

2. The barriers are not realistic. DOE to evaluate the same as per the latest guidelines for objective demonstration and assessment of barriers.

3. As the baseline is argued to be coal based boiler, an investment analysis is more appropriate for proving additionality. However DOE to check the basis for investment in the project at the time of investment decision. 

Please provide the response to my comments on the mail id: clean.development.mechanism.india@gmail.com

Author wishes to remain anonymous

Regards
Submitted by: CDM INDIA

1.	How many CDM projects are registered/under registration processes at Essar, Hazira?
2.	Is there any possibility to bundle all Essar CDM projects?
3.	How many local people were employed in last 3 years by Essar, as discussed during stake holder meeting?
4.	What is role and benefits for Denmark based project participant?
5.	What is the role of consultant Asia Carbon Emission in this CDM project?
6.	Monitoring is proposed only for generated CER (reduced GHG during that period), what about pollution generated from other plant in same premises? If GHG emitted from other plant, what will be monitoring criteria for that?

From
Hiral Mehta/Mahesh Pandya
Environmental Engineers
Paryavaran mitra
502, Raj Avenue, Bhaikakanagar road
Thaltej, Ahmedabad - 380059
Telefax - 079-26851321/1801
 
Submitted by: paryavaranmitra


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs