Bundled Yeonggwang(II)-Yecheon PV (Photovoltaic) Power Plant Project in KHNP
[]
Host party(ies) Republic of Korea
Methodology(ies) AMS-I.D. ver. 17
Standardised Baselines N/A
Estimated annual reductions* 10,606
Start date of first crediting period. 31 Oct 12
Length of first crediting period. 10 years
DOE/AE Korean Standards Association
Period for comments 01 May 12 - 30 May 12
PP(s) for which DOE have a contractual obligation Korea Hydro & Nuclear Power Co., Ltd. (KHNP)
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (1498 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs