Grid-connected electricity generation from renewable source: Sete Lagoas Solar Power Plant
[]
Host party(ies) Brazil
Methodology(ies) AMS-I.D. ver. 17
Standardised Baselines N/A
Estimated annual reductions* 942
Start date of first crediting period. 05 Jan 13
Length of first crediting period. 7 years
DOE/AE TÜV NORD CERT GmbH
Period for comments 12 Jul 12 - 10 Aug 12
PP(s) for which DOE have a contractual obligation WayCarbon Soluçġes Ambientais e Projetos de Carbono Ltda.
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (719 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs