Hon Chong Waste Heat Recovery Power Plant
[]
Host party(ies) Viet Nam
Methodology(ies) AMS-III.Q. ver. 4
Standardised Baselines N/A
Estimated annual reductions* 25,198
Start date of first crediting period. 01 Jul 12
Length of first crediting period. 10 years
DOE/AE TÜV NORD CERT GmbH
Period for comments 04 Aug 11 - 02 Sep 11
PP(s) for which DOE have a contractual obligation Holcim (Vietnam) Ltd.
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (1212 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs