CECEP Gansu Yumen Changma Daba North Wind Farm Project
[]
Host party(ies) China
Methodology(ies) ACM0002 ver. 12
Standardised Baselines N/A
Estimated annual reductions* 90,531
Start date of first crediting period. 01 Nov 12
Length of first crediting period. 7 years
DOE/AE TUEV-RHEIN
Period for comments 03 Dec 11 - 01 Jan 12
PP(s) for which DOE have a contractual obligation CECEP Wind Power (Gansu) Co.,Ltd
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (3152 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs