Fuyang China United Cement Corporation Ltd. Increasing Blend In Cement Production Project
[]
Host party(ies) China
Methodology(ies) ACM0005 ver. 5
Standardised Baselines N/A
Estimated annual reductions* 90,715
Start date of first crediting period. 01 Jan 12
Length of first crediting period. 10 years
DOE/AE TUEV-RHEIN
Period for comments 20 Jan 11 - 18 Feb 11
PP(s) for which DOE have a contractual obligation Fuyang China United Cement Corporation Ltd.
Gazprom Marketing & Trading Singapore Pte. Ltd.
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (1480 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs