Sichuan Jinwa Hydropower Project
[]
Host party(ies) China
Methodology(ies) ACM0002 ver. 12
Standardised Baselines N/A
Estimated annual reductions* 844,057
Start date of first crediting period. 01 Mar 11
Length of first crediting period. 7 years
DOE/AE TÜV SÜD South Asia Private Limited
Period for comments 22 Sep 10 - 21 Oct 10
PP(s) for which DOE have a contractual obligation Sichuan Chuantou Tianwanhe Development Co.,
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (539 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs