Waste Heat Recovery and Utilisation for Power Generation Project of Hunan Conch Cement Company Limited
[]
Host party(ies) China
Methodology(ies) ACM0012 ver. 3
Standardised Baselines N/A
Estimated annual reductions* 61,798
Start date of first crediting period. 01 Jan 10
Length of first crediting period. 10 years
DOE/AE DNV-CUK
Period for comments 27 May 09 - 25 Jun 09
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (594 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
Investment analysis appears to be excluding VAT from the electricity tariff. Investment analysis in this case should be performed INcluding the VAT because it represents the saving the cement plant makes in electricity payments to the grid.
Submitted by: The Face


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs