Xinjiang Dabancheng Sanchang Phase IV Wind Power Project
[]
Host party(ies) China
Methodology(ies) ACM0002 ver. 9
Standardised Baselines N/A
Estimated annual reductions* 142,283
Start date of first crediting period. 01 Jan 10
Length of first crediting period. 7 years
DOE/AE DNV-CUK
Period for comments 07 Apr 09 - 06 May 09
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (507 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
1.Project is not additional, please refer EB 41, annex 45 sensitivity analysis indiactes that the bench mark is crossed w.r.t 10% increase in tariff and generation.Requesting DOE to check the additionality (Investment analysis).
2. Monitoring plan is not as per the approved meth

Jhonson
Green solutions
Submitted by: jhonson


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs