Zhangjiakou City Qiaoxi District Central Heating Project
[]
Host party(ies) China
Methodology(ies) AM0058 ver. 3
Standardised Baselines N/A
Estimated annual reductions* 156,803
Start date of first crediting period. 01 Nov 11
Length of first crediting period. 10 years
DOE/AE Germanischer
Period for comments 20 Jul 11 - 18 Aug 11
PP(s) for which DOE have a contractual obligation EnBW Trading GmbH
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (968 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
The State Development Planning Commission (SDPC), the State Economic and Trade Commission (SETC), the Ministry of Construction (MOC) and the State Environmental Protection Administration (SEPA) on August 22, 2000 jointly issued the Regulations Concerning the Development of Cogeneration (http://www.rzjs.gov.cn/rqb/flfg/008.htm). It is indicated in Article 16 that centralized heating system instead of scattered small boilers should be applied for residential areas in heat distribution network in cities. This is an E- policy implemented before 11/11/2001. Hence the project activity is baseline.

In addition, the charge from end user legislated in local policy is against the national regulation (http://club.china.com/data/thread/1011/2718/53/76/3_1.html), and it is suspicious such clauses are meant to divert investment cost.
Submitted by: yure


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs