1.25 MW Wind Power Project by Aqua Alloys, India
[]
Host party(ies) India
Methodology(ies) AMS-I.F.
Standardised Baselines N/A
Estimated annual reductions* 1,711
Start date of first crediting period. 30 Dec 10
Length of first crediting period. 10 years
DOE/AE RINA Services S.p.A.
Period for comments 22 Jul 10 - 20 Aug 10
PP(s) for which DOE have a contractual obligation Aqua Alloys Private Limited (AAPL)
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (3117 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
What was the basis of PLF consideration of 16.95%. the consideration seems very low in comparison to the actual PLF of that area.?

whether other benefits as per the policies were considered while calculating the IRR.
Submitted by: Arnab deb


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs