Waste heat recovery based power generation project - Shree Ganesh Metaliks Limited
[]
Host party(ies) India
Methodology(ies) AMS-III.Q. ver. 4
Standardised Baselines N/A
Estimated annual reductions* 36,216
Start date of first crediting period. 01 Jan 12
Length of first crediting period. 10 years
DOE/AE TÜV NORD CERT GmbH
Period for comments 15 Aug 11 - 13 Sep 11
PP(s) for which DOE have a contractual obligation M/s Shree Ganesh Metaliks Ltd.
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (686 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
How GHG emissions will be reduced on account of the proposed project activity is not provided in the PDD.

2.	What is the power demand of the plant? What is the source of power prior to project activity? It is not clear whether only grid was the source before implementation of the proposed project activity. 

3.	It is clear from the PDD that the generated electricity is used for captive purposes, then why the generated electricity (at 11 KV) is stepped up to 33 KV and connected to 33 KV CSEB grid line. What is the need of this kind of design? The electrical layout comprises of generation, step up and step down transformers need to be demonstrated in the PDD.

4.	The value of quantity of flue gas generated mentioned in section A.2 and Section A.4.2 is not consistent. Waste energy and WECM stream is not adequately defined in the PDD. How is it proved that waste gas is termed as waste energy? It is not properly defined as per Methodology AMS III Q in the PDD. Pls. clarify.
5. 	When was the  plant commissioned? What is the status of the proposed project activity? How long flue gas is being wasted without utilised?

6.	As per EB51 Annex 59 Para9, for projects in which the electricity was being produced for captive consumption the benchmark of the core business was considered to be appropriate, as the project was considered to be an investment in the operation of the core business. PP has taken grid connectivity as benchmark which is wrong. The low risk projects cannot be compared with high risk projects. Because the proposed project activity could be developed only by the project developer and nobody else. So WACC could not be taken as benchmark. Pls. take internal benchmark as benchmark for determination of additonality. 
7.	When was DPR for captive power plant prepared? Since the project is existing one, the amount of waste heat utilized in the project activity that was released into the atmosphere prior to implementation of proposed project can be measured by direct measurements of energy content and amount of the waste gas from the date of commissioning of kiln prior to the start of the project activity. But why PP has chosen energy bills and process plant data to prove this. Pls. clarify.

8.	During emergency shutdown of kiln and turbine tripping, what is the source of power generation? It is not demonstrated with evidences that during the abnormal condition i. e emergency shutdown of the plant; waste gas shall be accounted for. What are the precautions and provision taken to ensure that waste gas /energy are not accounted for the calculation of emission reduction? Pls. clarify. Refer B.2
9.	Power tariff is not appropriate parameter to be included in the sensitivity analysis. PLF, no of hours operating and O&M charges are to be included in the sensitivity analysis. Refer B.5.

10.	The following are to be calculated indirectly and recorded on daily basis. Specific quantity of flue gas generated/end product of kiln (qwcm/product), Specific quantity of flue gas produced/ fuel fired in kiln), Specific quantity of fuel fired in kiln/end product of kiln.  These aspects are not documented with justification in the PDD. These parameters should be monitored so as to cross check the actual quantity of waste gas generated.  Quantity of end product in the kiln, quantity of fuel fired should be cross checked with sales and purchase department respectively.
11.	When the PP did not mention other barriers like technical, Infrastructure barrier etc. for the additionality, Common practice is not strong enough to prove that the project activity is business as usual.
Submitted by: sud

Guidelines for completing the PDD states, “Explain and justify key assumptions and rationales. Provide relevant documentation or references. Illustrate in a transparent manner all data used to assess the additionality of the project activity (variables, parameters, data sources etc.)”.

PP should have read this, Consultant should know this and DOE should not have over looked this requirement. The webhosted PDD does not disclose even a single assumption or rationale; the PDD is most non-transparent as it does not disclose even a single assumption / data used to assess the additionality. PDD is secretive and DOE did not even care to look at it before webhosting. It is absolutely non-transparent and totally against the CDM guidelines.

The project is non-additional. If it is additional, then there are no reasons why the PP and consultant should hide the input parameters and DOE accept it.  

This project should not be taken up for validation unless it is re webhosted conforming to the guidelines for completing the PDD. EB may kindly take note of this and requested not to entertain this project for registration if submitted, unless it is re-webhosted with all details and information. 
Submitted by: Karthikeyan


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs