Tuppadahalli Wind Energy Project
[]
Host party(ies) India
Methodology(ies) ACM0002 ver. 12
Standardised Baselines N/A
Estimated annual reductions* 128,809
Start date of first crediting period. 01 Apr 11
Length of first crediting period. 7 years
DOE/AE Bureau Veritas India Pvt. Ltd.
Period for comments 04 Feb 11 - 05 Mar 11
PP(s) for which DOE have a contractual obligation Tuppadahalli Energy India Pvt. Ltd
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (2027 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
1.	How GHG emission is reduced due to the project activity is not demonstrated in the PDD. Please clarify. 
2.	The break up mentioned in the section B.4 doesn’t match with URL at the footnote. Pls. explain. 
3.	The calculation of project IRR is not as per “Guidance on the Assessment of Investment Analysis’ Version 03, EB 51, Annex 58”.
4.	Derating factor, array efficiency of the wind energy system is not depicted in the PDD. Pls. clarify. 
5.	Debt/Equity ratio should be based on recent investment done by the Project proponent. 
6.	Whether pre-tax or post tax IRR is selected is not demonstrated in the PDD.
7.	Prior consideration of CDM which is important for the determination of additionality is not documented in the section B.5 of the PDD.  
Submitted by: mathew


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs