Line 5 & 6 - PFC emission reduction at DUBAL
[]
Host party(ies) United Arab Emirates
Methodology(ies) AM0030 ver. 3
Standardised Baselines N/A
Estimated annual reductions* 21,515
Start date of first crediting period. 01 Oct 10
Length of first crediting period. 10 years
DOE/AE DNV-CUK
Period for comments 13 Feb 10 - 14 Mar 10
PP(s) for which DOE have a contractual obligation Abu Dhabi Future Energy Company
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (336 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
This is a good project, contributing to the reduction of PFC emissions, PFC has very 
high GWP. This project should be registered
as CDM
Submitted by: Sanjeev Sharma


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs