Inner-Mongolia Xingan League Keyouzhongqi Emuting Gaole 49.5MW Wind Farm Phase I
[]
Host party(ies) China
Methodology(ies) ACM0002 ver. 12
Standardised Baselines N/A
Estimated annual reductions* 117,476
Start date of first crediting period. 01 Jan 12
Length of first crediting period. 7 years
DOE/AE TUEV-RHEIN
Period for comments 09 Nov 11 - 08 Dec 11
PP(s) for which DOE have a contractual obligation Keyouzhongqi Tianyou New Energy Co., Ltd.
Vitol.S.A.
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (652 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs