Yugong River 24MW Hydropower Project
[]
Host party(ies) China
Methodology(ies) ACM0002 ver. 12
Standardised Baselines N/A
Estimated annual reductions* 72,432
Start date of first crediting period. 01 Jan 12
Length of first crediting period. 7 years
DOE/AE LRQA Ltd
Period for comments 11 Mar 11 - 09 Apr 11
PP(s) for which DOE have a contractual obligation Carbon Asset Management Sweden Pte Ltd
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (467 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
Comment (1057 KB) submitted by: Lidia Krivorotova on behalf of Dusia

Please, give the possibility to see PDD. 
Thank you. 
Submitted by: Lidia Krivorotova


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs