Wind Power Project by Plasti Surge Industries Pvt. Ltd.
[]
Host party(ies) India
Methodology(ies) AMS-I.D. ver. 15
Standardised Baselines N/A
Estimated annual reductions* 3,861
Start date of first crediting period. 31 Dec 10
Length of first crediting period. 10 years
DOE/AE SIRIM
Period for comments 21 May 10 - 19 Jun 10
PP(s) for which DOE have a contractual obligation Plasti Surge Industries Pvt. Ltd.
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (499 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
1. If the Project IRR is so below benchmark why is the proponent going ahead with the project. moreover PDD doesnot show whether after considering CDM benefit the project IRR crosses the Benchmark. which is highly unlikely as the project's return is very low. so, a justification is needed for the same.

DOE to check whether the project IRR crosses the Benchmark after considering the CDM benefit with market rate of CER and Cnversion rate of Euro during the project decision time.
Submitted by: Arnab deb


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs