1 MW Ground Mounted Solar Power Project at IPSHEM, Goa by ONGC
[]
Host party(ies) India
Methodology(ies) AMS-I.D. ver. 18
Standardised Baselines N/A
Estimated annual reductions* 1,485
Proposed start date of PA 25 Apr 18
Start date of first crediting period. N/A
Length of first crediting period. 7 years
DOE/AE LGAI Technological Center, S.A.
Period for comments 01 Dec 20 - 30 Dec 20 (23:59:59 GMT)
PP(s) for which DOE have a contractual obligation Oil and Natural Gas Corporation Ltd.
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (654 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs