1.5 MW Wind Power Project in Sinnar, Maharashtra
[]
Host party(ies) India
Methodology(ies) AMS-I.D. ver. 15
Standardised Baselines N/A
Estimated annual reductions* 2,980
Start date of first crediting period. 01 Jun 10
Length of first crediting period. 10 years
DOE/AE Germanischer
Period for comments 19 Jan 10 - 17 Feb 10
PP(s) for which DOE have a contractual obligation METCON India Engineers and Contractors (METCON)
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (746 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs