7.5 MW Wind Power project in Jodhpur, Rajasthan
[]
Host party(ies) India
Methodology(ies) AMS-I.D. ver. 13
Standardised Baselines N/A
Estimated annual reductions* 14,028
Start date of first crediting period. 01 Jun 09
Length of first crediting period. 10 years
DOE/AE SGS-UKL
Period for comments 15 Apr 09 - 14 May 09
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (755 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
The fact that the project activity was commissioned on 31st March 2008 and the engagement letter with CDM consultant was done on 25th October 2008 is an indication that prior consideration of CDM was not taken seriously. Further, the DNA Meeting was conducted on 19th March 2009; almost one year after the project was commissioned. Even stake holders meeting was done only in Jan 2009. Hence I would request DOE to seriously investigate the seriousness of PRIOR CDM consideration in this project
Submitted by: A.R.Ravi Kumar


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs