7.5 MW Lubuk Gadang Small Hydropower Plant at West Sumatera, Indonesia
[]
Host party(ies) Indonesia
Methodology(ies) AMS-I.D. ver. 17
Standardised Baselines N/A
Estimated annual reductions* 31,180
Start date of first crediting period. 01 Aug 13
Length of first crediting period. 7 years
DOE/AE TUEV-RHEIN
Period for comments 13 Jul 11 - 11 Aug 11
PP(s) for which DOE have a contractual obligation PT Selo Kencana Energi
Swiss Carbon Assets Ltd.
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (726 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs