Co-generation works of Beijing electronic zone project
[]
Host party(ies) China
Methodology(ies) AM0029 ver. 3
Standardised Baselines N/A
Estimated annual reductions* 155,366
Start date of first crediting period. 01 Jul 11
Length of first crediting period. 7 years
DOE/AE DNV-CUK
Period for comments 29 Jul 10 - 27 Aug 10
PP(s) for which DOE have a contractual obligation EcoSecurities International Limited
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (603 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
1. the methodology is applicable o electricity generation plant, not cogeneration plant.

2. in Annual Report on China's Energy Development (2009), it indicates that the natual gas is short in supply as the demand rate increases 14.9% annually while the supply rate increases only 12.7%. This causes the estimated shortage of 20 billion cubic meters (bcm) in 2010, 60 bcm in 2015 and 100 bcm in 2020.

3. finacial analysis doesn't consider the benefit from input VAT deduction.
Submitted by: tianmaiqi


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs