Fujian Zhangpu Liuao 3rd phase Wind Power Project
[]
Host party(ies) China
Methodology(ies) ACM0002 ver. 7
Standardised Baselines N/A
Estimated annual reductions* 47,761
Start date of first crediting period. 01 Jun 09
Length of first crediting period. 7 years
DOE/AE DNV-CUK
Period for comments 17 Oct 08 - 15 Nov 08
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (471 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs