20 MW Biomass Power Project at Godawari Power and Ispat Limited, Chhattisgarh
[]
Host party(ies) India
Methodology(ies) ACM0018
Standardised Baselines N/A
Estimated annual reductions* 93,381
Start date of first crediting period. 01 Nov 11
Length of first crediting period. 10 years
DOE/AE KBS Certification Services Limited
Period for comments 22 Jun 11 - 21 Jul 11
PP(s) for which DOE have a contractual obligation Godawari Power and Ispat Ltd.
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (843 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
The DOE to check all the comments received during the last publishing on the UNFCCC website for international stake holder consultation process. This is one of the worst PDD I have ever seen on UN web site. Why was it web hosted in the first place by the previous DOE and this DOE? Is this the way DOE’s do their due diligence to web host the projects? What due diligence the present DOE has done to undertake this project? This is clearly a cooked up project which is strictly a non-CDM project. There is no additionality in whatever form including financial additionality. The equipment for this project was procured from China and other places at a very low cost? Project cost shown looks to be fabricated for such second hand equipment. Check the payment proof for all the costs shown in the project. Payment checks should be done with the bank also to tally the same as shown by the PP. The start date of the project is tampered? This project belongs to a date which is later than August 2008. This project must have been given notice to UNFCCC and DNA. Notices not given, so date is back dated to be safe. Is this right and acceptable? Any further validation of this project will make these DOE’s unsafe and ready for suspension.  
For power and biomass what are the baselines? How are you establishing and proving the base lines? The PDD does not clearly indicate the approach. It is very confusing. For biomass as per PDD, it will be burnt or left in the open area for decay- baseline. But in the additionality section a price for that “burnt/left over” biomass is fixed as INR 2000. What is this? This project clearly does not have proper base line, additionality. More over the documents are forged  to show more project cost and date of purchase orders changed to cover the default committed on notices to be sent to DNA and UNFCCC. DOE must check the project suitability for CDM and also verify some critical issues before web hosting. This was not done both the times by different DOE’s. What is this DOE doing? Do they have staff to do proper PDD completeness checks? Or they are simply web hosting any PDD given by the PP’s? This project was never a CDM project and will never become one. This project must be rejected by the DOE right away without any further waste of time.

Submitted by: sud

•	.What is the steam and power demand of the plant? What is the source of steam and power? These aspects have to be documented clearly in the relevant sections for better clarity and transparency.
•	.During the turbine tripping, from where power will be sourced is not mentioned. DOE has to check whether any DG sets or grid connectivity is subscribed. If yes, these aspects should be documented in the PDD.
•	.The supplementary fuel and auxiliary electricity consumption of the power plant is not documented in the PDD.
•	. If any boiler (fossil fuel fired) is used prior to implementation of project activity, DOE has to check the remaining life period of the boiler. If it is in end of life, then baseline for steam cannot be taken. Since the usage of fossil fuel fired boiler is not demonstrated explicitly in the PDD, the conclusion is not ensured.
•	. CDM consultancy agreement and correspondence needs to be ascertained to ensure the real and continuous actions taken in procuring CDM benefits.
•	. PLF and no of operating hours should be based on realistic phenomenon and as per EB guideline. DOE has to check.
•	. Efficiency of boilers both in baseline and project activity needs to be ascertained by the manufacturer and DOE has to check the authenticity. 
•	. Measurement of quantity of biomass fired in the boiler should be direct method. Indirect measurement is not acceptable. It is done indirectly, moisture loss, carpet loss needs to be monitored. DOE has to check.
•	. When plant is commissioned and when project activity is going to be commissioned needs to be validated clearly.
•	Generation based on PLF and no of operating hours of the plant should be included for the sensitivity analysis. Pls clarify.
•	Chronology of events is missing. Whether the real and continuous action taking place in getting CDM benefits is not evident from the PDD. DOE has to check. 
•	During tripping of turbine due to emergency, electricity will be imported. This aspect is not discussed in the PDD. Pls clarify
•	How CDM benefits will alleviate the technical barriers as elucidated in the PDD.
•	Gross generation, auxiliary consumption, in-plant consumption of electricity should be monitored if not possible indirectly. 
•	Steam generation, pressure of steam temperature of steam, feed water inlet temperature should be monitored on hourly basis. Auxiliary fuel that will be consumed should be monitored. 
	
Submitted by: lawrance

If you carefully read through the PDD it is confirmed that this is not a genuine CDM project at all. What is the exact project cost? The project cost is covering what? The machinery is second hand purchased or fresh and new from an OEM? In either case DOE to check all the quotations, proposals, purchase orders, invoices, way bills, transport bills, proof of payments like bank statements. 
DOE to check with banks by way of written confirmation the amount transacted, to whom the money is paid, when the money is paid, is the party paid is the correct party as shown in the purchase orders. It is very clear that the values, party names, dates are fabricated and misrepresented in this project. DOE should terminate their contract for this project immediately. This is the only way out to protect the value of CDM process. It looks like PP is purchasing second hand or second quality equipment by inflating the purchase order values and invoices. This must be probed thoroughly and real values to taken for additionality calculation. Then I’m sure the additionality is not there at all in this project. How is the base line defined in this project? Base line is hypothetically defined with no proper evidences and proper justification. 
DOE cannot take the base line as suggested by the PDD.  Please note that there are no emissions beyond the real and factual base line. This project definitely qualifies for zero CER’s, not even one CER. DOE cannot assume values and things as giving by this PP. Whatever values are considered throughout the project in all documents including the real DPR (not the one prepared for CDM, the one given to the banks and others), they must be validated, verified and double checked. Do not ask PP for DPR. Ask the parties who have been given DPR by the PP. Get directly from the bank and others by each page of the DPR and Feasibulity report signed. Such document can be considered as a real DPR or FR. This project is genuinely a fabricated, false and misinterpreted project with no base line and additionality.  
Submitted by: alexander

	DOE to write to the party who prepared the DPR/FR which is submitted to the banks and other agencies and the same is verified against the one submitted to the DOE by PP/Consultant. 

	DOE must not entertain this project any more if found the DPR/FR is tamprered with at any point in time. PP can not give different DPR’s and FR’s. They must submit only the one given to Banks and other agencies while obtaining loans and decision making time. 


	DOE to ensure that the PDD values are consistent and ensure that the CDM project is a genuine project

	DoE to check the Detailed Project Report and Feasibility Report which is submitted to the other agencies and Banks by Project owner and ensure that the values match with the DPR/FR  submitted to DoE also. 


	Careful study must be done so that the DPR/FR is not in different versions made and submitted with different purposes to different agencies, which is totally unacceptable, illegal and unethical. 

	Project owner should show some undertaking letter from bank manager to DoE stating that both DPR’s are same. These kinds of letters should not be accepted and entertained by DoE at face value, but must be checked independently. While collecting the DPR/FR from banks and other agencies, all DPR/FR pages should be counter signed by Banks and other agencies so that the real DPR/FR given to other parties by the PP/Consultant is same as the one submitted to DOE. 


	DPR/FR values must be probed fully. DOE must take a written undertaking from the PP/Consultant about the list of parties to whom this DPR/FR is submitted and for what purposes. Then DOE should cross check with all the parties and confirm that the same DPR/FR is submitted to all the parties correctly without any changes. DOE must not accept any reports and undertakings from PP/Consultant. DOE must make independent evaluation and use totally different parties without informing the PP or Consultant to cross check the facts. 


	Has the PP considered the CDM revenues while envisaging the project? Without CDM the project was not viable, is it right? This project is having a debt component? Then how bankers or lenders gave the loan? Have the bankers or lenders considered the CDM revenues while agreeing to give loan to this projects? If not this project should be rejected right away by DOE by terminating the contract forthwith. If yes, where is the proof? What is the date of the evidence document from bank? Is this document printed now a days or earlier. DOE to independently check the same. If the document is  available from Bank it must be checked from all angles so that it is genuine and not forged and date changed by putting back dated. This is normally done, DOE to be aware of this please. Please check the communication the PP had during that time with banks, emails and postal receipts and the weights and dates mentioned on the receipts. Do not believe in courier bills and receipts since these can be cooked up easily. Insist on government owned postal service receipts only. If the project is fully equity project then on what basis the PP has invested full equity in to the project while considering the CDM revenue? DOE to check the same in detail and bring out the facts. Is there any past record of this PP to invest or not to invest at returns what he is talking about in this project? Proper evidences must be reviewed and digged out by the DOE and take decision on the project based on established facts. Do not ask documents from PP, DOE to collect the same from different sources to do independent evaluation. 

	 How is the base line defined in this project? Is Base line hypothetically defined with no proper evidences and proper justification? In such case, DOE cannot take the base line as suggested by the PDD.  Please check that there are real emission reductions beyond the real and factual base line. It may so happen that this project qualifies for no CER’s. DOE cannot assume values and things as giving by this PP. Whatever values are considered throughout the project in all documents including the real DPR (not the one prepared for CDM, the one given to the banks and others), they must be validated, verified and double checked. Do not ask PP for DPR. Ask the parties who have been given DPR by the PP. Get directly from the bank and others by each page of the DPR and Feasibility report signed. Such document can be considered as a real DPR or FR. UNFCCC CDM process cannot be degraded by fabricating and misinterpreting the project base line and additionality.  



	From DOE side which auditor has done marketing and business development for acquiring this business of validating this project? With whom he or she was co-ordinating at PP or CER buyer? The same person who has done the marketing and business development to acquire the business do validation or participate in any manner what so ever in the validation process? One cannot do like that. It is against the accreditation rules and norms followed since ages. DOE should send auditors from different offices or countries to do this validation audit. DOE must take care of impartiality and accreditation rules. Due to the targets set by the DOE managements auditors are doing marketing and meeting clients and giving promises that the project will be taken care. Is it acceptable and fair? This must be stopped. No auditor should do marketing. Only non-auditing staff should do marketing. DOE to ensure the same please. 


	If applicable only: Is these machines, equipment was a part of any bundle of CDM activity envisaged and developed earlier. DOE to check the same through independent sources also. Once some bundles are non-additional and getting negative validation from a DOE, PP is rolling out the same project as an individual project which is not a CDM project at all. DOE to verify the same from independent sources and also take undertaking in the form of an affidavit from the PP’s that any misrepresentation or false statement with respect this would attract strict legal action from UNFCCC and DOE. Furthermore the registered project must be de-registered in case of any future findings contradicting the submissions made by the project owner.  



	DOE to be more careful so that this is a genuine CDM project. What is the exact project cost? The project cost is covering what? Each value considered must be validated with proof. The machinery is second hand purchased or fresh and new from an OEM? In either case DOE to check all the quotations, proposals, purchase orders, invoices, way bills, transport bills, proof of payments like bank statements. DOE to check with banks by way of written confirmation the amount transacted, to whom the money is paid, when the money is paid, is the party paid is the correct party as shown in the purchase orders. It may so happen that the values, party names, dates are fabricated and misrepresented in this project. DOE should terminate their contract for this project immediately. This is the only way out to protect the value of CDM process. If the PP is purchasing second hand or second quality equipment and inflating the purchase order values and invoices, this must be probed thoroughly and real values to taken for additionality calculation. Then I’m sure the additionality is not there at all in such a situation.

	Is the project equipment purchased second hand equipment or sourced from cheap foreign sources? If yes, the issue must be probed by DOE since invoices will invariably be inflated and forged. Total project costs mentioned by PP will not be the same as originals. Hence no additionality. These facts must be probed in full by DOE by checking all documents and money transactions along with bank statements and certified accounts by a legally acceptable financial analyst. 

Submitted by: sud

It looks like from the PDD the start date of the project is tampered for sure. This must be verified and let the truth come out. The culprits of forgery and malpractices must be brought to book. Why DOE has taken up such a bad project? Is there any pressure on DOE or some cake offered to DOE? They DOE must terminate this project immediately. DOE to check the offer letters originals and get the same verified in writing from the OEM’s and submitted parties. Where is the OEM supplier agreement original? DOE to check for the same. Is it prepared later with date and amounts changed to suit the project workings? For sure yes. This is not acceptable. 
DOE to check all purchase orders originals with the receiver of purchase orders i.e. the supplier of equipment. This PO confirmation to the DOE must be in writing from a board level person of the equipment supplier to avoid any malpractices and forgery. Then DOE to check for the invoices dates, payment amounts and date of payments made with all original documents and reconfirm with the parties involved and the banks for the accuracy of amounts, dates and parties involved. Same analysis and due diligence work to be repeated for “Notice to Proceed” as written in the case of Purchase order as above. DOE to check all “Notice to Proceed” originals with the receiver of “Notice to Proceed” i.e. the supplier of equipment or Engineering Procurement & Construction Contractor. This “Notice to proceed” and EPC contract confirmation to the DOE must be in writing from a board level person of the equipment supplier and EPC contractor to avoid any malpractices and forgery. Then DOE to check for the invoices dates, payment amounts and date of payments made with all original documents and reconfirm with the parties involved and the banks for the accuracy of amounts, dates and parties involved.
 DOE to check OEM supplier agreements, EPC contractor agreements, “Notice to proceed” letters, and Invoices raised. I’m sure DOE will catch the malpractices happened in this project. All the parties involved in this matter must be brought to justice. DOE must not support this kind of forgeries and malpractices. DOE cannot afford to close their eyes to this kind of malpractices. 
Submitted by: sud

It is evident from the PDD that the values are consistent and it is definitely forged and cooked up values to show a non CDM project as a CDM project. What is this? DoE to check the Detailed Project Report and Feasibility Report which is submitted to the other agencies and Banks by Project owner and ensure that the values match with the DPR/FR  submitted to DoE also. After careful study of PDD it is found that DPR/FR is in different versions made and submitted with different purposes to different agencies which is totally unacceptable, illegal and unethical. PP/Consultant may show some undertaking letter from bank manager to DoE stating that both DPR’s are same. These kinds of letters should not be accepted and entertained by DoE. While collecting the DPR/FR from banks and other agencies, all DPR/FR pages should be counter signed by Banks and other agencies so that the real DPR/FR given to other parties by the PP/Consultant is same as the one submitted to DOE. In this particular project there is clear cut evidence that DPR/FR values are changed/ fabricated mischievously and intentionally. This must be probed fully. DOE must take a written undertaking from the PP/Consultant about the list of parties to whom this DPR/FR is submitted and for what purposes. Then DOE should cross check with all the parties and confirm that the same DPR/FR is submitted to all the parties correctly without any changes. DOE must not accept any reports and undertakings from PP/Consultant. DOE must make independent evaluation and use totally different parties without informing the PP or Consultant to cross check the facts. DOE to write to the party who prepared the DPR/FR which is submitted to the banks and other agencies and the same is verified against the one submitted to the DOE by PP/Consultant. This project is a fabricated and fake CDM project and must be rejected by the DOE right away. DOE should not support this kind of projects otherwise CDM EB should suspend this DOE for at least one year. 
Submitted by: sud

If you carefully read through the PDD it is confirmed that this is not a genuine CDM project at all. What is the exact project cost? The project cost is covering what? The machinery is second hand purchased or fresh and new from an OEM? In either case DOE to check all the quotations, proposals, purchase orders, invoices, way bills, transport bills, proof of payments like bank statements. 
DOE to check with banks by way of written confirmation the amount transacted, to whom the money is paid, when the money is paid, is the party paid is the correct party as shown in the purchase orders. It is very clear that the values, party names, dates are fabricated and misrepresented in this project. DOE should terminate their contract for this project immediately. This is the only way out to protect the value of CDM process. It looks like PP is purchasing second hand or second quality equipment by inflating the purchase order values and invoices. This must be probed thoroughly and real values to taken for additionality calculation. Then I’m sure the additionality is not there at all in this project. How is the base line defined in this project? Base line is hypothetically defined with no proper evidences and proper justification. 
DOE cannot take the base line as suggested by the PDD.  Please note that there are no emissions beyond the real and factual base line. This project definitely qualifies for zero CER’s, not even one CER. DOE cannot assume values and things as giving by this PP. Whatever values are considered throughout the project in all documents including the real DPR (not the one prepared for CDM, the one given to the banks and others), they must be validated, verified and double checked. Do not ask PP for DPR. Ask the parties who have been given DPR by the PP. Get directly from the bank and others by each page of the DPR and Feasibulity report signed. Such document can be considered as a real DPR or FR. This project is genuinely a fabricated, false and misinterpreted project with no base line and additionality.  
Submitted by: sud

1)	DOE to ensure that the PDD values are consistent and ensure that the CDM project is a genuine project.
2)	DoE to check the Detailed Project Report and Feasibility Report which is submitted to the other agencies and Banks by Project owner and ensure that the values match with the DPR/FR  submitted to DoE also. 
3)	Careful study must be done so that the DPR/FR is not in different versions made and submitted with different purposes to different agencies, which is totally unacceptable, illegal and unethical. 
4)	Project owner should show some undertaking letter from bank manager to DoE stating that both DPR’s are same. These kinds of letters should not be accepted and entertained by DoE at face value, but must be checked independently. While collecting the DPR/FR from banks and other agencies, all DPR/FR pages should be counter signed by Banks and other agencies so that the real DPR/FR given to other parties by the PP/Consultant is same as the one submitted to DOE. 
5)	DPR/FR values must be probed fully. DOE must take a written undertaking from the PP/Consultant about the list of parties to whom this DPR/FR is submitted and for what purposes. Then DOE should cross check with all the parties and confirm that the same DPR/FR is submitted to all the parties correctly without any changes. DOE must not accept any reports and undertakings from PP/Consultant. DOE must make independent evaluation and use totally different parties without informing the PP or Consultant to cross check the facts. 
6)	DOE to write to the party who prepared the DPR/FR which is submitted to the banks and other agencies and the same is verified against the one submitted to the DOE by PP/Consultant. 
7)	DOE must not entertain this project any more if found the DPR/FR is tamprered with at any point in time. PP can not give different DPR’s and FR’s. They must submit only the one given to Banks and other agencies while obtaining loans and decision making time. 

8)	Has the PP considered the CDM revenues while envisaging the project? Without CDM the project was not viable, is it right? This project is having a debt component? Then how bankers or lenders gave the loan? Have the bankers or lenders considered the CDM revenues while agreeing to give loan to this projects? If not this project should be rejected right away by DOE by terminating the contract forthwith. If yes, where is the proof? What is the date of the evidence document from bank? Is this document printed now a days or earlier. DOE to independently check the same. If the document is  available from Bank it must be checked from all angles so that it is genuine and not forged and date changed by putting back dated. This is normally done, DOE to be aware of this please. Please check the communication the PP had during that time with banks, emails and postal receipts and the weights and dates mentioned on the receipts. Do not believe in courier bills and receipts since these can be cooked up easily. Insist on government owned postal service receipts only. If the project is fully equity project then on what basis the PP has invested full equity in to the project while considering the CDM revenue? DOE to check the same in detail and bring out the facts. Is there any past record of this PP to invest or not to invest at returns what he is talking about in this project? Proper evidences must be reviewed and digged out by the DOE and take decision on the project based on established facts. Do not ask documents from PP, DOE to collect the same from different sources to do independent evaluation. 

9)	Is the project equipment purchased second hand equipment or sourced from cheap foreign sources? If yes, the issue must be probed by DOE since invoices will invariably be inflated and forged. Total project costs mentioned by PP will not be the same as originals. Hence no additionality. These facts must be probed in full by DOE by checking all documents and money transactions along with bank statements and certified accounts by a legally acceptable financial analyst. 

10)	From DOE side which auditor has done marketing and business development for acquiring this business of validating this project? With whom he or she was co-ordinating at PP or CER buyer? The same person who has done the marketing and business development to acquire the business do validation or participate in any manner what so ever in the validation process? One cannot do like that. It is against the accreditation rules and norms followed since ages. DOE should send auditors from different offices or countries to do this validation audit. DOE must take care of impartiality and accreditation rules. Due to the targets set by the DOE managements auditors are doing marketing and meeting clients and giving promises that the project will be taken care. Is it acceptable and fair? This must be stopped. No auditor should do marketing. Only non-auditing staff should do marketing. DOE to ensure the same please. 


11)	If applicable only: Is these machines, equipment was a part of any bundle of CDM activity envisaged and developed earlier. DOE to check the same through independent sources also. Once some bundles are non-additional and getting negative validation from a DOE, PP is rolling out the same project as an individual project which is not a CDM project at all. DOE to verify the same from independent sources and also take undertaking in the form of an affidavit from the PP’s that any misrepresentation or false statement with respect this would attract strict legal action from UNFCCC and DOE. Furthermore the registered project must be de-registered in case of any future findings contradicting the submissions made by the project owner.  

12)	DOE to be more careful so that this is a genuine CDM project. What is the exact project cost? The project cost is covering what? Each value considered must be validated with proof. The machinery is second hand purchased or fresh and new from an OEM? In either case DOE to check all the quotations, proposals, purchase orders, invoices, way bills, transport bills, proof of payments like bank statements. DOE to check with banks by way of written confirmation the amount transacted, to whom the money is paid, when the money is paid, is the party paid is the correct party as shown in the purchase orders. It may so happen that the values, party names, dates are fabricated and misrepresented in this project. DOE should terminate their contract for this project immediately. This is the only way out to protect the value of CDM process. If the PP is purchasing second hand or second quality equipment and inflating the purchase order values and invoices, this must be probed thoroughly and real values to taken for additionality calculation. Then I’m sure the additionality is not there at all in such a situation.

13)	 How is the base line defined in this project? Is Base line hypothetically defined with no proper evidences and proper justification? In such case, DOE cannot take the base line as suggested by the PDD.  Please check that there are real emission reductions beyond the real and factual base line. It may so happen that this project qualifies for no CER’s. DOE cannot assume values and things as giving by this PP. Whatever values are considered throughout the project in all documents including the real DPR (not the one prepared for CDM, the one given to the banks and others), they must be validated, verified and double checked. Do not ask PP for DPR. Ask the parties who have been given DPR by the PP. Get directly from the bank and others by each page of the DPR and Feasibility report signed. Such document can be considered as a real DPR or FR. UNFCCC CDM process cannot be degraded by fabricating and misinterpreting the project base line and additionality.  
Submitted by: sud

1.	What is the status of the project implementation? If construction is started, how PP will justify that CDM benefit is the deciding factor for the project implementation. What will happen to the project if the project fails to get registered?

2.	Whether the project is green field project, or power expansion capacity expansion, or energy efficiency projects, or fuel switch projects .This aspect is not discussed in the section A of PDD.

3.	How GHG emission is reduced by the project activity is not discussed in the PDD. This is required as per CDM guidelines.

4.	Technical parameters should include boilers, turbines, BoP, etc.

5.	Whether the project activity is grid connected or captive purpose is not mentioned. 

6.	Project boundary is not clearly depicted in the PDD. It should be as per methodology ACM18. Transportation of biomass, site where biomass will be dumped should be documented in the PDD. But PDD is silent on this aspect.

7.	The specific situation of the project activity as per Meth ACM 18  not mentioned in the PDD.

8.	It is mentioned in the B.2 that biomass residues used for this project will be obtained off-site from the nearby area. But where is the justification or proof.   Just mentioning is not sufficient. 

9.	What is the proof that coal will not be used more than 50% in energy units. How much coal is proposed to use in the system. Why it is not mentioned in the section B.2. How PP will justify the argument. 

10.	Applicability conditions as per ACM18 are not justified completely in the PDD.

11.	In section B.4, it is argued that P1 (i. e project activity without CDM revenue) is not credible alternative. If that is the case, how the construction has been started without CDM revenue. 
12.	In section B.4, the justification for P6. Is not correct. “The installation of new power-only plants fired with biomass residues, or fossil fuels, or a combination of both, at the project site, using the same amount or less biomass residues than under scenario P1”. But is argued wrongly that “It is technologically impossible for new biomass residue fired power-only plant to provide the same amount of power using less biomass residues than under scenario P1.” Therefore, Alternative P6 needs to be justified properly. 

13.	The argument for P7 is not properly justified. It should be substantiated so as to satisfy the criteria.

14.	When defining plausible and credible alternative scenarios for power generation, the guidance below should be strictly followed as per meth:
• For any of the alternative scenarios described above, all assumptions with respect to installed capacities, load factors, energy efficiencies, fuel mixes, and equipment configuration, should be clearly described and justified in the CDM-PDD. The justification for existing plants should be based on the existing conditions of the plants and the justification for new plants, or changes to existing plants, should be based on design parameters selected considering realistic and credible alternative design options;
• The whole electricity generation under the project scenario, at the project site, must be considered. Therefore, whenever the project activity involves an increase in installed power generation capacity, an increase in electricity generation, and/or a change in electricity demand as compared to the historical situation, the baseline scenario should be determined for the overall power generated under the project activity, possibly including a combination of the different scenarios described above. This is particularly relevant for cases in which existing power plants have operated at the project site prior to the implementation of the project activity;

In cases where alternative scenarios include the installation of new power generation facilities at the project site other than the proposed project activity, the economically most attractive technology and fuel mix should be identified among those which provide the same service (i.e. the same power quantity), that are technologically available and that are in compliance with relevant regulations. The efficiency of the technology and the fuel type should be selected in a conservative manner, i.e. where several technologies and/or fuel types could be used and are similarly economically attractive, the least carbon intensive fuel type/the most efficient technology should be considered. Ensure that the selected technology represents at least common practice for new power plants in the respective industry sector, in the country or region, excluding CDM registered projects. 
If a power plant was already operated at the project site prior to the implementation of the project activity, it could be retired at the start of the project activity because it is replaced by the project plant, or it may initially be operated in parallel to the project plant and be retired at a future point in time (at the end of its lifetime). In such cases, the remaining technical lifetime of the existing equipment has to be determined and a baseline based on historical performance only applies until the existing power plant would have been replaced or retrofitted in the absence of the project activity. From that point of time, a different baseline shall apply.
Project participants should determine the age and the average technical lifetime of any existing power plant, taking into account common practices in the sector and country. The average technical lifetime may be determined based on industry surveys, statistics, technical literature or the practices of the responsible company regarding replacement schedules, e.g. based on historical replacement records for similar equipment. The average technical lifetime should be chosen in conservative manner, i.e. the earliest point in time should be chosen in cases where only a time frame can be estimated, and should be documented and justified in the CDM-PDD;
•  If the project activity supplies electricity partially or fully to (a) captive consumer(s), then alternatives considered for power generation should only include alternatives that can be implemented at the project site (e.g. P1, P2, P3, P4, P6 or P7) or the purchase of electricity from the grid (P5) but not the generation of power in plants established by the project participants at other locations; 

But PP does not follow this in the PDD.

15.	When defining plausible and credible alternative scenarios for the use of biomass residues, the guidance below should be strictly followed:
•  The baseline scenario for the use of biomass residues should be separately identified for different categories of biomass residues, covering the whole amount of biomass residues supposed to be used in the project activity along the crediting period, and consistent with the alternative scenarios selected for power generation (Scenarios P above);
•  A category of biomass residues is defined by three attributes: (1) its type (i.e. bagasse, rice husks, empty fruit bunches, etc.); (2) its source (e.g. produced on-site, obtained from an identified biomass residues producer, obtained from a biomass residues market, etc.); and (3) its fate in the absence of the project activity (Scenarios B above);
•  For example, consider a project activity which includes the installation of a new biomass-only power plant, and the retrofit of an existing co-fired biomass-fossil-fuel power plant, which has historically used rice husks, produced on-site. Suppose that the project activity will use two types of biomass residues, rice husks (historical use plus an additional amount) and diverse agricultural residues (as additional biomass residues compared to the historical situation).
Further consider that the rice husks used in the project would come from two different sources, on-site production and off-site supply from an identified rice mill. Presumably, the rice husks produced on-site would have been partly used on-site for electricity generation and partly be dumped in the baseline. The rice husks procured off-site would have been dumped in the baseline. The diverse agricultural residues are purchased from a biomass retailer. For this example, four categories of biomass residues should be considered in the subsequent analysis, as illustrated in Table 2;
•  Explain and document transparently in the CDM-PDD, using a table similar to Table 2, which quantities of which biomass residues categories are used in which installation(s) under the project activity and what is their baseline scenario. The last column of Table 2 corresponds to the quantity of each category of biomass residues (tonnes). For the selection of the baseline scenario and demonstration of additionality, at the validation stage, an ex-ante estimation of these quantities should be provided. These quantities should be updated every year of the crediting period as part of the monitoring plan so as to reflect the actual use of biomass residues in the project scenario. These updated values should be used for emissions reductions calculations. Along the crediting period, new categories of biomass residues (i.e. new types, new sources, with different fate) can be used in the project activity. In this case, a new line should be added to the table as per Meth ACM18.

16.	What is the proof that in the absence of project activity, biomass will be dumped or left to decay under aerobic conditions (B1)? What is the proof? Is there any practice in around the region? I don’t think it will be left to decay or dumped. It has energy value that will waste these precious materials. The argument is not as per meth ACM18.

17.	The argument is not strong for Biomass alternatives B2 and B3. What is the proof? It should be argued based on some practice followed in the region. The argument is not correct. So B1, B3 cannot be considered as alternative.

18.	How the CDM revenue will alleviate the technical barriers. If CDM revenue does not alleviate the barriers then the project activity is not additional. 

19.	It is argued that in the absence of project activity, biomass will be dumped or left to decay which implies that the biomass is free. But in the investment barrier argument, the cost of biomass is mentioned as Rs.1095/T which is wrong. DOE has the responsibility to validate this. 

20.	Investment barrier argument should be based on meth. Not all aspects of investment barrier are demonstrated in the PDD.

Benchmark chosen based on PLR is not acceptable. Why internal benchmark is not taken as benchmark for argument. Why WACC is not taken as benchmark. The basis of calculating IRR is not mentioned. The benchmark should be based on  
(a) Government bond rates, increased by a suitable risk premium to reflect private investment and/or the project type, as substantiated by an independent (financial) expert or documented by official publicly available financial data;
(b)  Estimates of the cost of financing and required return on capital (e.g. commercial lending rates and guarantees required for the country and the type of project activity concerned), based on bankers views and private equity investors/funds required return on comparable projects;
(c)  A company internal financial benchmark (weighted average cost of capital of the company), only in the particular case that the project activity can only be implemented by the project participant. The project developers shall demonstrate that this financial benchmark has been consistently used in the past i.e. that project activities under similar conditions developed by the same company used the same financial benchmark;
(d)  A government/officially approved financial benchmark where, it can be demonstrated that such financial benchmarks are used for investment decisions;
(e)  Any other indicators, if the project participants can demonstrate that the above options are not applicable and their indicator is appropriately justified.

21.	The justification for low PLF is not provided in the PDD.

22.	Prior consideration of the CDM is not demonstrated adequately and chronology of events is not provided in the PDD.

 


Submitted by: lawrance

Paragaraph 8 , Sub-step 2(c) of Additionality Tool required PP to “Present the investment analysis in a transparent manner and provide all the relevant assumptions preferably in the CDM-PDD, or in separate annexes to the CDM-PDD, so that a reader can reproduce the analysis and obtain the same results”. However, the web hosted PDD hides information and is not transparent. For example, it does not give the number of working days assumed (one has to compute based on generation and cPLF factor given and arrive at 330 days), it does not give heat rate and calorific value of biomass; it does not state whether fossil fuel is going to be used with biomass or not; it does not give specific fuel consumption; it does not state whether the administrative, operating & maintenance expenses assumed at 5% per annum is 5% of project cost or sales revenue; likewise it does state whether wages and salaries assumed at 10% per annum is based on project cost or sales revenue. Therefore, the PDD does not conform to the requirement of Additionality Tool. The PDD should be re-webhosted with all assumptions and input parameters before being taken up for validation.

The project cost is high. CERC recommends a cost of Rs.4 crore/MW. This project, without turbine is projecting a cost of Rs.3.90 crore/MW. DOE should note that the project is already having a turbine which is connecting WHRB and AFBC boilers (see P.14 of PDD).  The biomass cost assumed is very high. There are other web hosted projects which have assumed price of Rs.1100/ton; CERC has recommended a cost of less than Rs.1000/ton. More than 60% of the power was exported to grid in 2009-10 (the total generation of November 2009 is incorrect). The tariff assumed is incorrect and is not as per CERC tariff order. It is much higher. The project is entitled to accelerated depreciation (80% plus 20% additional depreciation in the first year); the project is eligible for 10 year tax holiday. Since this is a part of the company, which is paying tax, the accelerated depreciation will enable the company to get tax saving, which should be taken into account as cash inflow. All these fiscal and financial benefits 

DOE should ensure that the PDD is re webhosted with all requisite information to ensure that a reader is able to reprdocue the analysis and obtain the same results.
Submitted by: Karthikeyan


The comment period is over.