China Resources New Energy Lianzhou Yanxi 49.8MW Wind Power Project
[]
Host party(ies) China
Methodology(ies) ACM0002 ver. 12
Standardised Baselines N/A
Estimated annual reductions* 81,578
Start date of first crediting period. 01 Mar 12
Length of first crediting period. 7 years
DOE/AE TUEV-RHEIN
Period for comments 29 Oct 11 - 27 Nov 11
PP(s) for which DOE have a contractual obligation China Resources New Energy (Lianzhou) Wind Power Co., Ltd.
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (1370 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
It was reported that the construction started in June 2011 (http://7j.sinohydro.com/sdcg/news/Show.asp?id=681&cat_id=28), which is before project approval and investment decision according to the timeline in PDD.
Submitted by: fengdian


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs