Submission of comments to the DOE/AE
|
Compilation of submitted inputs:
1. In India there is huge shortage of Natural Gas especially the irregular and interrupted supply of the Gas. At the same time the project proposed to use Natural gas which would further aggravated the problem. In that case the present user of the natural gas would be forced to switch to the alternative such as fossil fuel and ultimately the GHG would be released.
2. No plan has been submitted regarding use of 2% of the net revenue accrued from the sale of CER toward achieving the sustainable development goals.
3. The investment analysis is incomplete and fails to provide the data and assumptions necessary for reader to reproduce the result.
4. No information has been provided regarding the cost of fuel switch in the PDD.
5. As per the EIA report the noise level recorded in the individual process units exceeded the stipulated standards of Central Pollution Control Board (CPCB).
6. The PDD does not explain about identified training, monitoring and maintenance as per the Technology requirements for contractors / engineers by the client. There is no mention of field quality Assurance systems & procedures that are available at site, field quality plans and their approval.
7. Chronology of events with corresponding emails, letters need to be validated by DOE.
8. The leakage calculation is not correct as per applied meth AM29.
9. What is the basis for arriving discount factor since it has more bearing on the levelised cost.
10. The input values taken for calculation of levelised cost of generation are not provided. Pls. clarify.
11. The argument for opting out of other energy sources from the baseline is not adequately demonstrated in the PDD. Where is the proof for each of the argument? PP has duty to provide to all the points it raised to opting out of renewable and other sources.
12. The reason for excluding the power generation using natural gas with different technologies is not clear. It is mentioned in the PDD that the project activity is a combined cycle power plant with the modern state of art technology and significant efficiency improvement is not possible with current technology status to reduce GHG intensity any further. As CCPP is very efficient technology there are no higher efficient technologies available to the project proponent for power generation utilizing natural gas.
13. Project proponent conveniently hides the past history of the project and presents it as if it is a new project. DOE to check the prehistory of the project.
14. DOE to check the DPR, tender documents inviting proposals, tender correspondence, proposals etc. to clearly validate.
15. The PP states that they have considered 80% accelerated depreciation. However the PDD is silent on the tax shielding as a result from accelerated depreciation. PPs cleverly do not consider the accounting tax offsetting in their companies while calculating the IRR. This is evident from the recently registered projects and those requesting registration.
16. The DOE is therefore requested to critically analyze how the accelerated depreciation benefit has been taken into account and confirm the accounting of the cash inflows as a result of the negative tax liability in the initial years. DOE should not be misguided by the financial presented by the PP or consultant which are custom made for CDM purposes and not the actual financial considered at the investment decision. Note that considering cash inflows results in an increase in the IRR making wind projects a profitable venture.
17. Please also check the offer from WTG supplier and Purchase Order while validating the PLF. It may be so that the third party report which is made after investment decision making - indicates a lower PLF. The PLF seems to be very low. Also check the tariff order.
18. methodology selection is wrong – applicability condition 1 of AM0029 requires ‘The project activity is the construction and operation of a new natural gas fired grid-connected electricity generation plant.’ This project plant is only a modification of an existing plant that operated for many years now.
19. If the plant is just a retrofit, how baseline can be a coal based plant? Was it possible to retrofit this GTs to use coal? This is a ridiculous claim by behalf of PP and consultants.
20. Whether project has got Environment Clearance from Ministry of Environment & Forest, New Delhi? What are major conditions stipulated in Clearance?
21. Whether uninterrupted supply of Natural Gas has been ensured from suppliers for continuous operation? Whether gas will be provided from existing network of pipeline or modification is needed?
22. Host country is already encouraging sustainable development on basis of clean technology and cleaner fuel, in this case how this project meet additionality criteria of CDM process?
23. Whether Environment Public Hearing as process of Environment Clearance was arranged for this gas based power plant? If yes, what were major discussion and decisions of Environment Public Hearing?
24. Additionality
The methodology considers a project additional under the following circumstances
a) There is a more economically attractive and GHG intensive alternative available to the project activity (lower levelized cost when compared to the project activity); and
b) The project on a standalone basis is not financially attractive (low IRR as compared to standard industry benchmark)
While the PP has demonstrated that there is a more economically attractive option available as compared to the project activity, it has not demonstrated that the project on a standalone basis is not financially viable . As the project activity involves displacement of power on the grid and the alternative can be set up by any other entity as well, it needs to undertake a benchmark analysis. In order to perform benchmark analysis, the PP needs to take into account the tariff that it receives from the sale of power.
The plant is being setup as a Merchant Power Plant (MPP) and hence may not enter into a long term PPA. It is a well known fact that merchant power plants are very attractive, because they get higher tariff than PPA based power plants. An article in Powernomics is quoted here.
Submitted by: lasith
1) DOE to ensure that the PDD values are consistent and ensure that the CDM project is a genuine project.
2) DoE to check the Detailed Project Report and Feasibility Report which is submitted to the other agencies and Banks by Project owner and ensure that the values match with the DPR/FR submitted to DoE also.
3) Careful study must be done so that the DPR/FR is not in different versions made and submitted with different purposes to different agencies, which is totally unacceptable, illegal and unethical.
4) Project owner should show some undertaking letter from bank manager to DoE stating that both DPR’s are same. These kinds of letters should not be accepted and entertained by DoE at face value, but must be checked independently. While collecting the DPR/FR from banks and other agencies, all DPR/FR pages should be counter signed by Banks and other agencies so that the real DPR/FR given to other parties by the PP/Consultant is same as the one submitted to DOE.
5) DPR/FR values must be probed fully. DOE must take a written undertaking from the PP/Consultant about the list of parties to whom this DPR/FR is submitted and for what purposes. Then DOE should cross check with all the parties and confirm that the same DPR/FR is submitted to all the parties correctly without any changes. DOE must not accept any reports and undertakings from PP/Consultant. DOE must make independent evaluation and use totally different parties without informing the PP or Consultant to cross check the facts.
6) DOE to write to the party who prepared the DPR/FR which is submitted to the banks and other agencies and the same is verified against the one submitted to the DOE by PP/Consultant.
7) DOE must not entertain this project any more if found the DPR/FR is tamprered with at any point in time. PP can not give different DPR’s and FR’s. They must submit only the one given to Banks and other agencies while obtaining loans and decision making time.
8) Has the PP considered the CDM revenues while envisaging the project? Without CDM the project was not viable, is it right? This project is having a debt component? Then how bankers or lenders gave the loan? Have the bankers or lenders considered the CDM revenues while agreeing to give loan to this projects? If not this project should be rejected right away by DOE by terminating the contract forthwith. If yes, where is the proof? What is the date of the evidence document from bank? Is this document printed now a days or earlier. DOE to independently check the same. If the document is available from Bank it must be checked from all angles so that it is genuine and not forged and date changed by putting back dated. This is normally done, DOE to be aware of this please. Please check the communication the PP had during that time with banks, emails and postal receipts and the weights and dates mentioned on the receipts. Do not believe in courier bills and receipts since these can be cooked up easily. Insist on government owned postal service receipts only. If the project is fully equity project then on what basis the PP has invested full equity in to the project while considering the CDM revenue? DOE to check the same in detail and bring out the facts. Is there any past record of this PP to invest or not to invest at returns what he is talking about in this project? Proper evidences must be reviewed and digged out by the DOE and take decision on the project based on established facts. Do not ask documents from PP, DOE to collect the same from different sources to do independent evaluation.
9) Is the project equipment purchased second hand equipment or sourced from cheap foreign sources? If yes, the issue must be probed by DOE since invoices will invariably be inflated and forged. Total project costs mentioned by PP will not be the same as originals. Hence no additionality. These facts must be probed in full by DOE by checking all documents and money transactions along with bank statements and certified accounts by a legally acceptable financial analyst.
10) From DOE side which auditor has done marketing and business development for acquiring this business of validating this project? With whom he or she was co-ordinating at PP or CER buyer? The same person who has done the marketing and business development to acquire the business do validation or participate in any manner what so ever in the validation process? One cannot do like that. It is against the accreditation rules and norms followed since ages. DOE should send auditors from different offices or countries to do this validation audit. DOE must take care of impartiality and accreditation rules. Due to the targets set by the DOE managements auditors are doing marketing and meeting clients and giving promises that the project will be taken care. Is it acceptable and fair? This must be stopped. No auditor should do marketing. Only non-auditing staff should do marketing. DOE to ensure the same please.
11) If applicable only: Is these machines, equipment was a part of any bundle of CDM activity envisaged and developed earlier. DOE to check the same through independent sources also. Once some bundles are non-additional and getting negative validation from a DOE, PP is rolling out the same project as an individual project which is not a CDM project at all. DOE to verify the same from independent sources and also take undertaking in the form of an affidavit from the PP’s that any misrepresentation or false statement with respect this would attract strict legal action from UNFCCC and DOE. Furthermore the registered project must be de-registered in case of any future findings contradicting the submissions made by the project owner.
12) DOE to be more careful so that this is a genuine CDM project. What is the exact project cost? The project cost is covering what? Each value considered must be validated with proof. The machinery is second hand purchased or fresh and new from an OEM? In either case DOE to check all the quotations, proposals, purchase orders, invoices, way bills, transport bills, proof of payments like bank statements. DOE to check with banks by way of written confirmation the amount transacted, to whom the money is paid, when the money is paid, is the party paid is the correct party as shown in the purchase orders. It may so happen that the values, party names, dates are fabricated and misrepresented in this project. DOE should terminate their contract for this project immediately. This is the only way out to protect the value of CDM process. If the PP is purchasing second hand or second quality equipment and inflating the purchase order values and invoices, this must be probed thoroughly and real values to taken for additionality calculation. Then I’m sure the additionality is not there at all in such a situation.
13) How is the base line defined in this project? Is Base line hypothetically defined with no proper evidences and proper justification? In such case, DOE cannot take the base line as suggested by the PDD. Please check that there are real emission reductions beyond the real and factual base line. It may so happen that this project qualifies for no CER’s. DOE cannot assume values and things as giving by this PP. Whatever values are considered throughout the project in all documents including the real DPR (not the one prepared for CDM, the one given to the banks and others), they must be validated, verified and double checked. Do not ask PP for DPR. Ask the parties who have been given DPR by the PP. Get directly from the bank and others by each page of the DPR and Feasibility report signed. Such document can be considered as a real DPR or FR. UNFCCC CDM process cannot be degraded by fabricating and misinterpreting the project base line and additionality.
Submitted by: lasith
The comment period is over.
|
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: