Wind Project Activity by PPS Enviro Power Pvt. Limited
[]
Host party(ies) India
Methodology(ies) AMS-I.D. ver. 16
Standardised Baselines N/A
Estimated annual reductions* 5,469
Start date of first crediting period. 01 Jul 11
Length of first crediting period. 10 years
DOE/AE TÜV NORD CERT GmbH
Period for comments 28 Jan 11 - 26 Feb 11
PP(s) for which DOE have a contractual obligation PPS Enviro Power Pvt. Limited
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (334 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
•	DOE has to check, PLR range not demonstrated adequately. 
•	Justification of PLF is not provided. There is a huge difference between two projects. It should be based on guideline as provided by latest EB report. Pls. clarify. DOE has to validate this.
•	Prior consideration of CDM activity not demonstrated adequately in PDD clarifies.
•	DOE has to check, CER’s calculation and values is not consistent through out the PDD, clarify.
•	Transmission loss has to be justified properly. 
•	The date of investment decision is not provided transparently. It should be used generously in the PDD for clarity. 
•	Operating margin, build margin, combined margin is not as per “Tool for emission factor for an electricity system”. The tool is not used at all. Pls. calculate combined margin as per the tool. Pls. justify that grid emission factor calculated is as per CEA data latest version.
•	The project cost of the project should be based on offer and not on purchase order or tariff order.
•	O&M charges considered are on higher side. Pls. clarify. 
•	Justification of tariff rate is not provided.
Submitted by: Johan fernandis

1.	DOE to check the appropriateness of choosing PLR as the benchmark
2.	Even with a high PLF of 31% the project IRR is only 4.31 and it surpasses the benchmark to reach 12.75% with CER revenue-  needs to be checked
3.	Prior awareness of CDM is not evident in the PDD.
4.	Only after having purchased all the WTGs the PP had considered the CDM.
5.	In the long time gap of 23 months between the WTGs purchase, there was no activity to secure CDM status for the project 
6.	CER values in sections A 4.3 and B 6.4 do not match

Submitted by: Fleming

	There is no proper prior consideration of CDM and real and continuous action to support this project as CDM project.
	Why there is 9 month gap between the PP and RRB supporting for bundle CDM project, which shows that it is an after thought to prepare documents. DOE has to verify it RRB also and get return confirmation that copy of MOU dated 4/12/2007 is real or genuine one.
	When is the prior consideration real & continuous action for 3rd and 4th WTG’s, it is clear that cooked up CDM project by consultant and PP.
	Why there is a delay of six month between PO date WTG’s and LOI with core carbon Solutions Pvt. Ltd.
	The LOI and Core cabonX cooked documents so that the DOE has to check that for its genuineness. 
	Why the PP is clubbing two WTG’s given to one consultant shifting the 2 WTG’s with another consultant. 
Submitted by: Toni


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs