Gangani Small Hydro Electric Project
[]
Host party(ies) India
Methodology(ies) AMS-I.D. ver. 16
Standardised Baselines N/A
Estimated annual reductions* 37,953
Start date of first crediting period. 01 Jan 11
Length of first crediting period. 7 years
DOE/AE DNV-CUK
Period for comments 01 Jul 10 - 30 Jul 10
PP(s) for which DOE have a contractual obligation Agrinergy Pte Ltd
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (320 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
1. It is not clear whether the project return improves to cross or touch the benchmark established by the project proponent. if the return doesnot cross or touch the benchmark after availing CDM revenues then why does the proponent went ahead with the project.?

2. how can equity beta be justified for calculating WACC. as it is the riskiness of the return corresponding to equity. rather asset beta considering the unleverage effect is more appropriate as per financial books by aswath damodaran.

3. BSE 500 is of shorter time in comparison to BSE 200 or 100 or sensex 30. the shorter time period may correspond to higher noise and might not address the unsystematic variation in the market. for robustness the value of bse 200 should have been considered.
Submitted by: Arnab deb

Comment (968 KB) submitted by: Manoj Misra on behalf of Manoj Misra


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs