Small Hydroelectric Power Plants Projects: São Pedro, Carangola, Calheiros, São Simão, Funil, São Joaquim, Fumaça IV, Jataí, Irara, Bonfante, Monte Serrat, Santa Fé, hereafter referred to as group (“bundling”).
[]
Host party(ies) Brazil
Methodology(ies) ACM0002 ver. 13
Standardised Baselines N/A
Estimated annual reductions* 308,197
Start date of first crediting period. 01 Jan 13
Length of first crediting period. 10 years
DOE/AE RINA Services S.p.A.
Period for comments 05 Oct 12 - 03 Nov 12
PP(s) for which DOE have a contractual obligation Centrais Elétricas Brasileiras - Eletrobras-
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (3185 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs