Increased electricity generation from Ertan Hydropower Plant through Decision Support System optimization
[]
Host party(ies) China
Methodology(ies) AM0052 ver. 2
Standardised Baselines N/A
Estimated annual reductions* 500,026
Start date of first crediting period. 01 Jan 11
Length of first crediting period. 10 years
DOE/AE Germanischer
Period for comments 23 Apr 10 - 22 May 10
PP(s) for which DOE have a contractual obligation Ertan Hydropower Development Co., Ltd
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (884 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
The project operated in 2000 with 6*550MW capacity. Mr. Zhang Chaoran, Chinese Academy of Engineering (CAE) Academician, was the chief engieer for the project design. Mr. Zhang is also the chief engineer of Three Gorges Dam project. The project received many awards as of its advanced techonology. It is not convinced the project was not equipped with DSS. Many articles adopted the optimized system of Ertan project as example for DSS analysis. DSS is widely used in China such as the info listed in
http://www.nari.cn/files/200505271465.shtml
Submitted by: shuidian


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs