Rialma Companhia Energética I S/A. – Santa Edwiges I Small Hydro Power Plant – Small Scale CDM Project.
[]
Host party(ies) Brazil
Methodology(ies) AMS-I.D. ver. 8
Standardised Baselines N/A
Estimated annual reductions* 39,543
Start date of first crediting period. 01 Nov 06
Length of first crediting period. 7 years
DOE/AE Bureau Veritas India Pvt. Ltd.
Period for comments 12 Apr 06 - 11 May 06
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (539 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs