Jubilee Oil Field Associated Gas Recovery and Utilization Project
[]
Host party(ies) Ghana
Methodology(ies) AM0009 ver. 4
Standardised Baselines N/A
Estimated annual reductions* 2,342,845
Start date of first crediting period. 01 Jan 13
Length of first crediting period. 10 years
DOE/AE DNV-CUK
Period for comments 27 Aug 11 - 25 Sep 11
PP(s) for which DOE have a contractual obligation Carbon Ghana Ltd.
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (3024 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
Dear Carbon Ghana

We we recently under the Green Facility visited Ghana National Petroleum Company in Tema they told us that it is illegal to flare in Ghana from off-shore oilfields, and that they had already build most of the gaspipeline etc to the shore. So therefore it was not possible to make it a CDM project. How can you then do it?

Best regards
Joergen Fenhann
jqfe@risoe.dtu.dk
Submitted by: Joergen Fenhann


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs