Electricity generation through wind power project at Jodhpur, Rajasthan
[]
Host party(ies) India
Methodology(ies) AMS-I.D. ver. 13
Standardised Baselines N/A
Estimated annual reductions* 5,550
Start date of first crediting period. 01 Jun 09
Length of first crediting period. 10 years
DOE/AE RINA Services S.p.A.
Period for comments 18 Feb 09 - 19 Mar 09
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (2694 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs