15 MW Biomass Power Project by Shalivahana Green Energy Limited
[]
Host party(ies) India
Methodology(ies) AMS-I.D. ver. 17
Standardised Baselines N/A
Estimated annual reductions* 57,474
Start date of first crediting period. 01 Oct 11
Length of first crediting period. 10 years
DOE/AE TÜV NORD CERT GmbH
Period for comments 03 Aug 11 - 01 Sep 11
PP(s) for which DOE have a contractual obligation Shalivahana Green Energy Limited
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (740 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
The project cost is coming to Rs.56 mn., which is very high for this project. Madhya Pradesh ERC has suggested only Rs.42.5 mn./MW for biomass power projects

Biomass cost has been taken at Rs.1207 per ton and supplementary fuel at 1030 per ton.  This is high compared to MPERC recommended cost

This project is eligible for 100% depreciation and also tax holiday. These should be taken into account while demonstrating additionality

Other barrier given has financial implication and already included in the investment and sensitivity analyses. 
Submitted by: Karthikeyan


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs