Wayang Windu Phase 2 Geothermal Power Project
[]
Host party(ies) Indonesia
Methodology(ies) ACM0002 ver. 8
Standardised Baselines N/A
Estimated annual reductions* 804,099
Start date of first crediting period. 01 Jul 09
Length of first crediting period. 7 years
DOE/AE TÜV SÜD South Asia Private Limited
Period for comments 21 Jan 09 - 19 Feb 09
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (805 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs