70MW Solar Power Plant Project in Ba Ria - Vung Tau, Vietnam
[]
Host party(ies) Viet Nam
Methodology(ies) ACM0002 ver. 19
Standardised Baselines N/A
Estimated annual reductions* 81,675
Proposed start date of PA 27 Sep 18
Start date of first crediting period. 01 Jun 19
Length of first crediting period. 7 years
DOE/AE Korean Standards Association
Period for comments 14 May 19 - 12 Jun 19 (23:59:59 GMT)
PP(s) for which DOE have a contractual obligation SH Power Co.,Ltd
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (1297 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs