Grid Connected Wind Power Generation Project by Ruchi Soya Industries Limited in Madhya Pradesh
[]
Host party(ies) India
Methodology(ies) ACM0002 ver. 12
Standardised Baselines N/A
Estimated annual reductions* 21,127
Start date of first crediting period. 31 Dec 11
Length of first crediting period. 10 years
DOE/AE TÜV NORD CERT GmbH
Period for comments 24 Aug 11 - 22 Sep 11
PP(s) for which DOE have a contractual obligation Ruchi Soya Industries Limited
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (392 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
Will the PP explain the reasons for selecting BPLR of 8 banks and selecting the average BPLR of the selected banks?  Will the PP also explain the reasons for not selecting the lowest BPLR when the rate of interest paid by the PP will be much lower as the project has availed ECB loan? PP may also explain why the actual lending rate of loan is not considered as benchmark and how this benchmark conforms to guidance 13. 

When for the earlier project located in the same district and state, the PP has considered PLF of 25.68% without any derating, will the PP explain the reasons for reducing the PLF to 23.54% with derating at 1% after 10th year? 

When the O&M cost provided is twice as much as the O&M cost recommended by MPERC (and that too on a cost which is 25% more than the cost recommended by MPERC) and when the MPERC has not recommended any other cost other than O&M cost, will the PP clarify on what basis administrative expenses of Rs.0.6 mn and that too escalated at 10% per annum (while O&M cost is escalated only at 5% per annum) is claimed? Why should the PP incur this expenditure, when O&M contractor is required to look after from security to billing?  Finally, when the company is already having a few more projects in the same location, how is this cost justified?   
Submitted by: Karthikeyan


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs