Real Waste Heat Recovery CDM Project
[]
Host party(ies) India
Methodology(ies) ACM0012 ver. 3
Standardised Baselines N/A
Estimated annual reductions* 34,361
Start date of first crediting period. 01 Apr 10
Length of first crediting period. 10 years
DOE/AE Bureau Veritas India Pvt. Ltd.
Period for comments 26 Jan 10 - 24 Feb 10
PP(s) for which DOE have a contractual obligation Real Ispat & Power Ltd
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (3157 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
Story regarding "CDM consideration" is good, however, its still a story by Shri Lalit Kumar Singhania, Shri Vikas Thakur and Shri Kalhan Ganju (PDD writers as per Section B.8). How can the writer of the PDD explain the reason of a gap of more than 1 year between board decision to avail CDM benefits and hiring of first consultant. Also as stated in PDD if PP had discussions with Mr. Lalit Kumar Singhania while considering CDM revenues then why he was not approached if “first CDM consultants had failed to give satisfactory progress in the matter”.  Also there are no third party evidences to support the CDM consideration. The purpose of Annex 46, EB 41 is not just prior consideration but also that the PP took real and continuing action to secure CDM. 

- It is clear that the project is now commissioned. If it needed CDM revenues to be financially feasible then how is it operating without receiving a positive validation report till now?
Submitted by: Eforum Monitoring Team


The comment period is over.