Nam Cong 3 Hydropower Project
[]
Host party(ies) Viet Nam
Methodology(ies) AMS-I.D. ver. 17
Standardised Baselines N/A
Estimated annual reductions* 20,132
Start date of first crediting period. 01 Jan 12
Length of first crediting period. 10 years
DOE/AE TUEV-RHEIN
Period for comments 01 Oct 11 - 30 Oct 11
PP(s) for which DOE have a contractual obligation Lilama 10 Joint- Stock Company
Electrabel NV/SA
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (959 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
Comment of Nam Cong 3 Hydropower Project
The PP/Consultant faked on the tariff applied for the project, it is evident that the tariff was made up lower than it was those similar projects in the country. The avoid cost tariff published for the stakeholder consultation in 3rd August 2007 (http://www.icon.evn.com.vn/Home/Thoisu/tabid/162/TopicId/1/ItemId/100634/View/2/language/vi-VN/Default.aspx) before the CDM consideration date, the project need to applied the avoid cost tariff as decision 18 or whatever conservative. The DOE need to ensure that if the actual tariff of the project would be higher than stated in the PDD.
 
Submitted by: cdm.watch


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs