Sichuan Province Songpan County Muguadun Hydroelectric Project
[]
Host party(ies) China
Methodology(ies) ACM0002 ver. 12
Standardised Baselines N/A
Estimated annual reductions* 78,793
Start date of first crediting period. 01 Oct 11
Length of first crediting period. 7 years
DOE/AE LRQA Ltd
Period for comments 19 Oct 10 - 17 Nov 10
PP(s) for which DOE have a contractual obligation EcoSecurities International Limited
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (835 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
1.	Equipment Purchase Contract was signed on 09/08/2009. And the project was in operation since May 2010. However no equipment information based on manufacturer’s specifications is listed.
2.	SL 16-95 regulates that sensitivity analysis considers only 2 indicators, investment cost and revenue for small hydropower projects, which is different with the requirements of CDM.
3.	According to the material published by Sichuan Hydropower Engineering Academy, there are more than 4000 operational hydropower stations in Sichuan till the end of 2007, in which 59 are large scale projects. In addition, Yearbook of China Water Resources collects information of hydro projects above 25 MW. Yearbook of China Water Resources 2006 listed 40 hydro plants in Sichuan, 15 among them are large scale hydro plants. Hence the project list in common practice is far too incomplete, neither convincing.
Submitted by: shuidian


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs