Bundled Wind Project by Sahyadri Industries Limited
[]
Host party(ies) India
Methodology(ies) AMS-I.D. ver. 16
Standardised Baselines N/A
Estimated annual reductions* 8,692
Start date of first crediting period. 01 Jun 11
Length of first crediting period. 7 years
DOE/AE SIRIM
Period for comments 14 Jan 11 - 12 Feb 11
PP(s) for which DOE have a contractual obligation Sahyadri Industries Limited
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (666 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs