Methane recovery and its utilization as fuel at Tamil Nadu Newsprint and Papers Limited (TNPL)
[]
Host party(ies) India
Methodology(ies) AMS-III.H. ver. 12
Standardised Baselines N/A
Estimated annual reductions* 25,491
Start date of first crediting period. 01 Jan 10
Length of first crediting period. 10 years
DOE/AE TÜV NORD CERT GmbH
Period for comments 31 Jul 09 - 29 Aug 09
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (1423 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
It needs to be checked in the financial analysis (which can only be shown to DOE!!!), that they have actually considered the prevaling cost of the project of INR 495 lakhs and not the increased cost of project at INR 778 lakhs, i.e., estimated Cost-Benefit analysis at the time of project conceptualization.

Further, it needs to be checked about the environmental regulations regarding the treatment for waste streams and if it requires treating the waste to a certain parameters which can be done using the project UASB technology than Biogas thus produced would actually be a by product and therefore the cost of production of Lime using this by-product would be significantly lower than the price of Lime in the market and hence beneficial and non-additional.

DOE needs to be careful while checking the Financial ananlysis sheet as these are often manipulated and do not show the practical operational parameters.

Other barriers, "First of its Kind", common practice have really been misused and the technology is already being used in many of the paper industries, therefore, DOE needs to do their own reasearch and do not remain satisfied with the proofs presented by PP/Consultants. Also, how could the PP anticipate the "stabilization problem" of November 2008 while considering the project as CDM project!!! This is really not a supplimentaly argument to show the technological barrier. there has to be some realistic proofs regarding possible technical problem (not the dis-advantages, since every technology have some advantages and dis-advantages) at the project conpectualization time. 

Please consider that there are always some inherrent risk to any business and hence they are being rewarded in the form of some profits, every such usual business risk cannot be accounted under CDM barrier and the barrier of BWW and other technological barrier seems to be overdone.
Submitted by: Sonika


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs