Submission of comments to the DOE/AE
|
Compilation of submitted inputs:
1. In section A.2, is not transparent on: Pre-project scenario, baseline scenario and how project is reducing GHG emissions. PP should refer to the CDM PDD guidelines while writing the PDD
2. The web reference to the DNA site is not provided
3. PP is claiming the project area is a backward area. DOE to check whether as per the national guidelines the area falls under the backward area.
4. DOE to check whether the project activity really contributes to the social development of the region. DOE to verify whether the project has created any direct or indirect employment opportunities in the region.
5. A.4.1 is not as per the CDM PDD guidelines. PP has neither clearly explained the exact physical location nor the geophysical coordinates of the project activity.
6. In the section A.4.2, PP has mentioned sectoral scope as 1. However the correct notation for sectoral scope is 01.
7. In section A.4.3, PP fails to explain technical description in terms of equipments involved, lifetime of the equipment, efficiency, load factors of the equipments, energy and mass balance. PP has also not explained technology involved in the baseline and pre-project scenario, emission sources. PP has not explained the type of biomass residues which will be fired in the project. PP has claimed that the project is unique in the region as it has deployed an air cooler condenser. DOE to verify this.
8. Table mentioned in the section A.4.4 is not as per the CDM PDD guidelines.
9. In section B.2, PP has not categorized project activity as per the types prescribed in the meth. PP has not covered all the applicability conditions in the PDD.
10. The table in the section B.3 is not as per the meth. PP has not at all transparent on project boundary. PP should refer to the guidelines while writing the PDD. How a PDD without mentioning the clear geophysical coordinates/physical location, project boundary can be webhosted.
11. PP should clear their basics about the CDM. In the section b.4, PP has mentioned project activity without registered as CDM can not become a baseline alternative. This is completely wrong. Project without CDM registration can be considered as an alternative and then should be eliminated in the next steps of combined tool.
12. PP has eliminated alternative P6 that this alternative is not possible. How this alternative is not possible. PP would have installed a new biomass/fossil fuel fired power plant with less/same amount of fuel in the absence of the project activity. This approach is more conservative than simply choosing P4 which is power generation in grid. DOE to asses the possibility of this alternative. PP to provide a logical justification and has to demonstrate that this alternative can not be considered as a baseline scenario.
13. In P7, PP mentions using more biomass residue will result in low efficiency. On what basis PP is making such statements? Before making any such statements PP should think logically. The justification for eliminating this alternative is simply illogical. PP should check out whether the surplus biomass residue is available in the region or not. IF surplus biomass residue is available, PP can fire more amount of biomass residue in the absence of the project activity. DOE to clearly validate the possibility of this alternative.
14. PP provides the required quantity and the surplus available quantity of prospis juliflora. DOE to check the source for the same
15. It is terrible to see that a biomass residue which is having a market price can be dumped or decayed without any use. The selection of baseline alternative B1 is not at all conservative and logical. DOE to asses why this alternative is not possible if the julifora has a market.
16. PP has mentioned fuel used will be Prospis Julifora and agricultural residues. Which are these agricultural residues?
17. Justification to eliminate the B3 is again illogical. PP to provide an appropriate justification. If according to PP, julifora can be dumped or decayed then it has all the possibilities that that it can be burnt in an uncontrolled manner also. All these activities indicate that the julifora will not be used as a fuel which is completely wrong as it has a value.
18. Juliflora has been used as a fuel in the region (In fact PP uses it in the . How and why julifora can not be used as a fuel in the other existing plants or new plants (baseline plants)? The justifications to B4 and B5 are completely illogical.
19. PP fails to identify correct baseline alternatives in the context of their techno-commercial feasibility, local/national regulations and in the interest of conservativeness. Please clarify.
20. In the table in B.4, PP has mentioned boiler is co-fired. It means boiler uses fossil fuel also. Then why PP has not mentioned this before?
21. Will project avail REC benfits? This will be additional revenue in addition to the sale of electricity.
22. Under technological barrier, PP says, due to 100% firing of biomass residues coating formation will occur which will decrease temperature of the steam. If this is the case then how PP can fire 100% biomass in the boiler? Moreover, PP has further mentioned to fire biomass residues furnace size is increased. How increase in the furnace size is related with the firing of biomass? This seems illogical. According to PP, biomass residues have high alkali content and hence firing is difficult. If this would have been the case, other biomass based plants in the region would not have been operated. The entire technological barrier justification is not correct. It is very simple. If you conceive to use biomass residues, the boiler will be designed in such a way that it can fire the biomass residues without any significant problems and to run the boiler very smoothly, PP has to follow O&M instructions. DOE to check and verify PPs statements and to decide whether to accept this types of arguments which forms the additionality arguments.
23. PP has committed that fossil fuel plant does not face the so called technological barriers. It means that the installation of the fossil fuel fired plant is possible in the baseline situation. Please clarify.
24. PP claims common practice in India is cooling towers. Provide an evidence for this statement. On what basis the cost for air cooling system is derived?
25. If biomass availability is so unsure, then how the neghbouring plants in the region are running? Satara is basically a agriculatural zone. It grows sugarcane, bajara, soya, cotton etc. The economy of the region stands on the agriculture. If this is the case, PP facing biomass residue barrier can not be accepted. DOE to check this.
26. It seems that PP has proven the barrier only qualitatively and not quantitatively. How these barrier will impact the project returns? Read the guidelines on objective demonstration and assessment of barriers (Para 6, 7, 8 of the guidance). How PP has demonstrated increased risk in the technology results in an additional expense? Can this barrier be overcome with additional money (if yes, then it should be included as an expenses in the investment analysis).
27. The choice of financial indicator is not explained.
28. If PP refers to MERC tariff order 2005, then as per the order PLF is 80%. Then why PP has applied 65,75 and 80% of PLF. What is the basis?
29. How interest on working capital is higher than interest on term loan?
30. On what basis the cost of biomass is arrived?
31. Why only MAT is applicable and why not regular IT?
32. The basis for the assumptions used in the investment analysis is not mentioned transparently. DOE to check the basis for these assumptions and the appropriateness in line with Para 6 of EB51, Annex 58.
33. What does PP mean by earliest decision making date? PP seems to be unfamiliar with the CDM terms. This is simply illogical. You will always have only one decision date. Does this mean PP had investment decisions several times and then PP has selected the earliest date? This is foolish. DOE to check the investment decision document, to check the original book of the minutes of the meeting and to confirm if there are multiple investment decisions.
34. IF EARLISTE decision date (the term is really foolish) is Oct 2007. PP mentions the RBI BPLR for the month of Nov 2007 is 12.75-13.75%. Where as link provided opens a document which was published in the month of Aug 2008. This shows PP’s carless attitude towards the entire CDM process. With this kind of information mentioned in the PDD, its DOEs responsibility to thoroughly check the every aspect of the project.
35. The benchmark selected is not conservative. The lower range should be selected as the conservative approach. (i.e. 12.75%). PP to explain why this is not selected and how selection of 13% over 12.75% is conservative?
36. On what basis PP has mentioned the price as 20Euros? Even at 2007 the price was around 15 euros (max to max 17euros)?
37. In common practice analysis, PP mentions “….the following plants have intiated steps….”. The word following indicates to the reader that a list of the plants is mentioned below. However, there is no mention of a single “Following” plants. PP has so carelessly written the PDD that it has not understood that writing such things can mislead the reader.
38. There is no mention of real and continuous action, no CDM/project related chronology. PP to explain why this has not been included in the PDD if guidelines clearly mention to do so. The way PP has written the PDD shows carless attitude of PP, misleading attitude and less transparency. DOE should not webhost such PDDs which do not even cover such basic points.
39. It seems PP does not even know how to monitor the net quantity of electricity in the cases where project exports power to grid. It is normally measured through an energy meter which is sealed by MSEDCL. Once in a month, MSEDCL representative and PP representative takes a joint meter reading and then based on the reading PP raises an invoice. DOE to check this and PP to explain why it is misleading the readers by providing such type of information?
40. Is the emission factor for diesel mentioned is correct?
41. It seems PP has not read IPCC 2006 guidelines. Emission factor for coal is 74.1 tCO2/TJ while PP mentions 0.09827 tCO2/GJ. PP is writing anything in the PDD. Moreover, PP should used local /nationally available data before using IPCC data.
42. PP should also monitor the emissions due to competitive use of biomass residue.
43. B.7.1, data archiving not monitored
44. PP is again misleading the reader by not mentioning the date of local stakeholder meeting, comments received etc. It is doubtful, whether in real PP has conducted LSM. PP to interview the stakeholders who attended the meeting. This is very important aspect to make stakeholders aware about the initiative. With PP’s carless and misleading attitude which has reflected through PDD writing, conduction of the meeting is real or not is doubtful.
45. EB to review if all the above comments are answered appropriately or not.
Submitted by: Stacy Johnson
1. In section A.2, is not transparent on: Pre-project scenario, baseline scenario and how project is reducing GHG emissions. PP should refer to the CDM PDD guidelines while writing the PDD
2. The web reference to the DNA site is not provided
3. PP is claiming the project area is a backward area. DOE to check whether as per the national guidelines the area falls under the backward area.
4. DOE to check whether the project activity really contributes to the social development of the region. DOE to verify whether the project has created any direct or indirect employment opportunities in the region.
5. A.4.1 is not as per the CDM PDD guidelines. PP has neither clearly explained the exact physical location nor the geophysical coordinates of the project activity.
6. In the section A.4.2, PP has mentioned sectoral scope as 1. However the correct notation for sectoral scope is 01.
7. In section A.4.3, PP fails to explain technical description in terms of equipments involved, lifetime of the equipment, efficiency, load factors of the equipments, energy and mass balance. PP has also not explained technology involved in the baseline and pre-project scenario, emission sources. PP has not explained the type of biomass residues which will be fired in the project. PP has claimed that the project is unique in the region as it has deployed an air cooler condenser. DOE to verify this.
8. Table mentioned in the section A.4.4 is not as per the CDM PDD guidelines.
9. In section B.2, PP has not categorized project activity as per the types prescribed in the meth. PP has not covered all the applicability conditions in the PDD.
10. The table in the section B.3 is not as per the meth. PP has not at all transparent on project boundary. PP should refer to the guidelines while writing the PDD. How a PDD without mentioning the clear geophysical coordinates/physical location, project boundary can be webhosted.
11. PP should clear their basics about the CDM. In the section b.4, PP has mentioned project activity without registered as CDM can not become a baseline alternative. This is completely wrong. Project without CDM registration can be considered as an alternative and then should be eliminated in the next steps of combined tool.
12. PP has eliminated alternative P6 that this alternative is not possible. How this alternative is not possible. PP would have installed a new biomass/fossil fuel fired power plant with less/same amount of fuel in the absence of the project activity. This approach is more conservative than simply choosing P4 which is power generation in grid. DOE to asses the possibility of this alternative. PP to provide a logical justification and has to demonstrate that this alternative can not be considered as a baseline scenario.
13. In P7, PP mentions using more biomass residue will result in low efficiency. On what basis PP is making such statements? Before making any such statements PP should think logically. The justification for eliminating this alternative is simply illogical. PP should check out whether the surplus biomass residue is available in the region or not. IF surplus biomass residue is available, PP can fire more amount of biomass residue in the absence of the project activity. DOE to clearly validate the possibility of this alternative.
14. PP provides the required quantity and the surplus available quantity of prospis juliflora. DOE to check the source for the same
15. It is terrible to see that a biomass residue which is having a market price can be dumped or decayed without any use. The selection of baseline alternative B1 is not at all conservative and logical. DOE to asses why this alternative is not possible if the julifora has a market.
16. PP has mentioned fuel used will be Prospis Julifora and agricultural residues. Which are these agricultural residues?
17. Justification to eliminate the B3 is again illogical. PP to provide an appropriate justification. If according to PP, julifora can be dumped or decayed then it has all the possibilities that that it can be burnt in an uncontrolled manner also. All these activities indicate that the julifora will not be used as a fuel which is completely wrong as it has a value.
18. Juliflora has been used as a fuel in the region (In fact PP uses it in the . How and why julifora can not be used as a fuel in the other existing plants or new plants (baseline plants)? The justifications to B4 and B5 are completely illogical.
19. PP fails to identify correct baseline alternatives in the context of their techno-commercial feasibility, local/national regulations and in the interest of conservativeness. Please clarify.
20. In the table in B.4, PP has mentioned boiler is co-fired. It means boiler uses fossil fuel also. Then why PP has not mentioned this before?
21. Will project avail REC benfits? This will be additional revenue in addition to the sale of electricity.
22. Under technological barrier, PP says, due to 100% firing of biomass residues coating formation will occur which will decrease temperature of the steam. If this is the case then how PP can fire 100% biomass in the boiler? Moreover, PP has further mentioned to fire biomass residues furnace size is increased. How increase in the furnace size is related with the firing of biomass? This seems illogical. According to PP, biomass residues have high alkali content and hence firing is difficult. If this would have been the case, other biomass based plants in the region would not have been operated. The entire technological barrier justification is not correct. It is very simple. If you conceive to use biomass residues, the boiler will be designed in such a way that it can fire the biomass residues without any significant problems and to run the boiler very smoothly, PP has to follow O&M instructions. DOE to check and verify PPs statements and to decide whether to accept this types of arguments which forms the additionality arguments.
23. PP has committed that fossil fuel plant does not face the so called technological barriers. It means that the installation of the fossil fuel fired plant is possible in the baseline situation. Please clarify.
24. PP claims common practice in India is cooling towers. Provide an evidence for this statement. On what basis the cost for air cooling system is derived?
25. If biomass availability is so unsure, then how the neghbouring plants in the region are running? Satara is basically a agriculatural zone. It grows sugarcane, bajara, soya, cotton etc. The economy of the region stands on the agriculture. If this is the case, PP facing biomass residue barrier can not be accepted. DOE to check this.
26. It seems that PP has proven the barrier only qualitatively and not quantitatively. How these barrier will impact the project returns? Read the guidelines on objective demonstration and assessment of barriers (Para 6, 7, 8 of the guidance). How PP has demonstrated increased risk in the technology results in an additional expense? Can this barrier be overcome with additional money (if yes, then it should be included as an expenses in the investment analysis).
27. The choice of financial indicator is not explained.
28. If PP refers to MERC tariff order 2005, then as per the order PLF is 80%. Then why PP has applied 65,75 and 80% of PLF. What is the basis?
29. How interest on working capital is higher than interest on term loan?
30. On what basis the cost of biomass is arrived?
31. Why only MAT is applicable and why not regular IT?
32. The basis for the assumptions used in the investment analysis is not mentioned transparently. DOE to check the basis for these assumptions and the appropriateness in line with Para 6 of EB51, Annex 58.
33. What does PP mean by earliest decision making date? PP seems to be unfamiliar with the CDM terms. This is simply illogical. You will always have only one decision date. Does this mean PP had investment decisions several times and then PP has selected the earliest date? This is foolish. DOE to check the investment decision document, to check the original book of the minutes of the meeting and to confirm if there are multiple investment decisions.
34. IF EARLISTE decision date (the term is really foolish) is Oct 2007. PP mentions the RBI BPLR for the month of Nov 2007 is 12.75-13.75%. Where as link provided opens a document which was published in the month of Aug 2008. This shows PP’s carless attitude towards the entire CDM process. With this kind of information mentioned in the PDD, its DOEs responsibility to thoroughly check the every aspect of the project.
35. The benchmark selected is not conservative. The lower range should be selected as the conservative approach. (i.e. 12.75%). PP to explain why this is not selected and how selection of 13% over 12.75% is conservative?
36. On what basis PP has mentioned the price as 20Euros? Even at 2007 the price was around 15 euros (max to max 17euros)?
37. In common practice analysis, PP mentions “….the following plants have intiated steps….”. The word following indicates to the reader that a list of the plants is mentioned below. However, there is no mention of a single “Following” plants. PP has so carelessly written the PDD that it has not understood that writing such things can mislead the reader.
38. There is no mention of real and continuous action, no CDM/project related chronology. PP to explain why this has not been included in the PDD if guidelines clearly mention to do so. The way PP has written the PDD shows carless attitude of PP, misleading attitude and less transparency. DOE should not webhost such PDDs which do not even cover such basic points.
39. It seems PP does not even know how to monitor the net quantity of electricity in the cases where project exports power to grid. It is normally measured through an energy meter which is sealed by MSEDCL. Once in a month, MSEDCL representative and PP representative takes a joint meter reading and then based on the reading PP raises an invoice. DOE to check this and PP to explain why it is misleading the readers by providing such type of information?
40. Is the emission factor for diesel mentioned is correct?
41. It seems PP has not read IPCC 2006 guidelines. Emission factor for coal is 74.1 tCO2/TJ while PP mentions 0.09827 tCO2/GJ. PP is writing anything in the PDD. Moreover, PP should used local /nationally available data before using IPCC data.
42. PP should also monitor the emissions due to competitive use of biomass residue.
43. B.7.1, data archiving not monitored
44. PP is again misleading the reader by not mentioning the date of local stakeholder meeting, comments received etc. It is doubtful, whether in real PP has conducted LSM. PP to interview the stakeholders who attended the meeting. This is very important aspect to make stakeholders aware about the initiative. With PP’s carless and misleading attitude which has reflected through PDD writing, conduction of the meeting is real or not is doubtful.
45. EB to review if all the above comments are answered appropriately or not.
Submitted by: Stacy Johnson
Comment (26 KB)
Submitted by: nancy johan