Jilin Da’an Dagangzi Wind Power Project Phase IV
[]
Host party(ies) China
Methodology(ies) ACM0002 ver. 11
Standardised Baselines N/A
Estimated annual reductions* 97,377
Start date of first crediting period. 01 Jan 11
Length of first crediting period. 7 years
DOE/AE Korean Foundation for Quality
Period for comments 20 Jul 10 - 18 Aug 10
PP(s) for which DOE have a contractual obligation EcoSecurities International Limited
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (461 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
Jilin Da'an Dagangzi Wind Farm Phase 2, 3 and 4 started construction in Apr., May and Jun. 2008. Three phase wind farms were put into operation in Dec. 2008, Mar. and Jun. 2009 separately. Tariff approved by Jilin Price Bureau for Phase 2, 3 and 4 was 0.61 yuan/kWh, implemented since 24 Nov. 2009.
Submitted by: fengdian


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs